Project

General

Profile

Actions

Issues

Filters

Apply Clear

Estimated time: 19438.00 Spent time: 5453.00

# Tracker Status Priority Subject Assignee Total estimated time Total spent time Updated
5410 Project progress work New Normal [Internal Design] 0.00 27 Jan 2026 16:11 Actions
5409 Project progress work New Normal [Requirement definition] 0.00 27 Jan 2026 16:11 Actions
5408 Parent project In Progress Normal [PJ260013] Operation monitoring system for ShinDengen Phase01 Nattapol Poeam 0.00 0.00 27 Jan 2026 16:11 Actions
5406 Project progress work New Normal [Installation&On-site support] 0.00 27 Jan 2026 13:55 Actions
5405 Project progress work New Normal [Coding] 0.00 27 Jan 2026 13:55 Actions
5404 Project progress work New Normal [Internal Design] 0.00 27 Jan 2026 13:54 Actions
5403 Project progress work New Normal [Requirement definition] 0.00 27 Jan 2026 13:54 Actions
5402 Parent project In Progress Normal [PJ260011] Operation monitoring system for ShinDengen add screen Nattapol Poeam 0.00 0.00 27 Jan 2026 13:54 Actions
5401 Project progress work New Normal [Installation&On-site support] 104.00 0.00 25 Mar 2026 15:25 Actions
5400 Project progress work New Normal [Coding] 48.00 0.00 11 Mar 2026 10:15 Actions
5399 Project progress work New Normal [Internal Design] 0.00 0.00 06 Feb 2026 11:34 Actions
5398 Project progress work New Normal [Requirement Definition] 0.00 0.00 06 Feb 2026 11:24 Actions
5397 Parent project In Progress Normal [PJ260010] Infrastructure IoT system for NTN Manufacturing(Thailand) Hardware PT Nattapol Poeam 152.00 0.00 25 Mar 2026 15:25 Actions
4464 Project progress work New Normal [Installation&On-site support] Report preventive maintenance summary Phatthadon Inthachot 40.00 0.00 17 Jan 2026 10:29 Actions
4463 Project progress work New Normal [Installation&On-site support] Preventive maintenance Phatthadon Inthachot 16.00 0.00 17 Jan 2026 10:28 Actions
4462 Project progress work New Normal [Installation&On-site support] Phatthadon Inthachot 56.00 0.00 17 Jan 2026 10:29 Actions
4460 Project progress work In Progress Normal [Internal Design] Phatthadon Inthachot 80.00 0.00 05 Mar 2026 15:48 Actions
4458 Parent project In Progress Normal [PJ260006] Camera system Preventive maintenance for STV Nattapol Poeam 160.00 0.00 05 Mar 2026 15:48 Actions
4448 Project progress work New Normal [Installation&On-site support] 0.00 16 Jan 2026 14:35 Actions
4447 Project progress work New Normal [Coding] 0.00 16 Jan 2026 14:35 Actions
4446 Project progress work New Normal [Internal Design] 0.00 16 Jan 2026 14:35 Actions
4445 Project progress work New Normal [Requirement definition] 0.00 16 Jan 2026 14:35 Actions
4444 Project progress work New Normal [Installation&On-site support] 0.00 16 Jan 2026 14:33 Actions
4443 Project progress work New Normal [Coding] 0.00 16 Jan 2026 14:33 Actions
4442 Project progress work New Normal [Internal Design] 0.00 16 Jan 2026 14:33 Actions
(151-175/520) Per page: 25, 50, 100

Also available in: Atom CSV PDF