Estimated time: 20886.00 Spent time: 6338.00

# Tracker Status Priority Subject Assignee Total estimated time Total spent time Updated
6741 Parent project In Progress Normal [PJ260036] Demo kit for Keyence SJ-bar Exhibition Nattapol Poeam 0.00 0.00 26 Feb 2026 11:21 Actions
6740 Project progress work New Normal [Installation&On-site support] 8.00 0.00 18 Mar 2026 10:33 Actions
6739 Project progress work New Normal [Coding] 0.00 26 Feb 2026 11:00 Actions
6738 Project progress work New Normal [Internal Design] 0.00 26 Feb 2026 10:59 Actions
6737 Project progress work New Normal [Requirement definition] 0.00 26 Feb 2026 10:59 Actions
6731 Parent project In Progress Normal [PJ260035] Traceability system for TOYO ADVANCED Nattapol Poeam 8.00 0.00 18 Mar 2026 10:33 Actions
6690 Project progress work New Normal [Issue] 120.00 0.00 11 Mar 2026 11:38 Actions
6654 Parent project In Progress Normal [PJ260027] Hardware unit sets Karnthida Wannasiwaporn 0.00 25 Feb 2026 14:24 Actions
6653 Project progress work New Normal [Installation&On-site support] 0.00 17 Feb 2026 10:46 Actions
6652 Project progress work New Normal [Coding] 0.00 17 Feb 2026 10:46 Actions
6651 Project progress work New Normal [Internal Design] 0.00 17 Feb 2026 10:46 Actions
6650 Project progress work New Normal [Requirement definition] 0.00 17 Feb 2026 10:45 Actions
6649 Parent project In Progress Normal [PJ260026] Two-point verification handy terminal application modification Surat Duangchiaw 0.00 0.00 13 Mar 2026 16:02 Actions
6648 Project progress work New Normal [Installation&On-site support] 16.00 0.00 18 Mar 2026 10:30 Actions
6647 Project progress work New Normal [Coding] 144.00 0.00 12 Mar 2026 16:01 Actions
6646 Project progress work New Normal [Internal Design] 0.00 17 Feb 2026 10:47 Actions
6645 Project progress work New Normal [Requirement definition] 0.00 17 Feb 2026 10:47 Actions
6644 Parent project In Progress Normal [PJ260025] Shipping dashboard monitor Nattapol Poeam 160.00 0.00 18 Mar 2026 10:30 Actions
6641 Project progress work New Normal [Internal design] System Design Nattapol Poeam 448.00 0.00 13 Feb 2026 15:48 Actions
6640 Project progress work New Normal [Requirement definition] Software service application development Nattapol Poeam 0.00 13 Feb 2026 15:46 Actions
6639 Project progress work New Normal [Requirement definition] Software development Nattapol Poeam 0.00 13 Feb 2026 15:44 Actions
6626 Project progress work New Normal [Installation&On-site support] Software installation Nattapol Poeam 0.00 13 Feb 2026 15:25 Actions
6625 Project progress work New Normal [Installation&On-site support] Hardware configuration Nattapol Poeam 0.00 13 Feb 2026 15:24 Actions
6624 Project progress work New Normal [Installation&On-site support] Hardware server installation Nattapol Poeam 0.00 13 Feb 2026 15:22 Actions
6623 Project progress work New Normal [Requirement definition] Software development Nattapol Poeam 0.00 13 Feb 2026 15:14 Actions