Estimated time: 18934.00 Spent time: 7923.40

# Tracker Status Priority Subject Assignee Total estimated time Total spent time Updated
3322 Project progress work New Normal [Coding] DB Seteup and modification Line 2 Worawit Khantamool 8.00 0.00 19 Dec 2025 09:26 Actions
3321 Project progress work New Normal [Coding] Validation check Signal & Information Pattanasak Chaonchom 0.00 19 Dec 2025 09:24 Actions
3320 Project progress work New Normal [Coding] WDT Configuration Line 5 Pattanasak Chaonchom 0.00 19 Dec 2025 09:22 Actions
3319 Project progress work New Normal [Coding] Validation check Signal & Information Line 4 Pattanasak Chaonchom 0.00 19 Dec 2025 09:24 Actions
3318 Project progress work New Normal [Coding] WDT Configuration Line 4 Pattanasak Chaonchom 0.00 19 Dec 2025 09:21 Actions
3317 Project progress work New Normal [Coding] Validation check Signal & Information Line 3 Pattanasak Chaonchom 8.00 0.00 19 Dec 2025 09:23 Actions
3316 Project progress work New Normal [Coding] WDT Configuration Line 3 Pattanasak Chaonchom 8.00 0.00 19 Dec 2025 09:19 Actions
3305 Project progress work New Normal [Installation&On-site support] 136.00 0.00 19 Dec 2025 10:39 Actions
3304 Project progress work New Normal [Coding] 40.00 0.00 19 Dec 2025 09:29 Actions
3303 Project progress work New Normal [Internal Design] 248.00 0.00 19 Dec 2025 09:12 Actions
3301 Project progress work In Progress Normal [Installation&On-site support] Go live Pattanasak Chaonchom 16.00 0.00 18 Dec 2025 14:35 Actions
3284 Project progress work New Normal [Coding] Quotation Master Lux Aubon 0.00 13 Dec 2025 11:13 Actions
3283 Project progress work New Normal [Coding] PO Merchandize Order FIX Lux Aubon 0.00 13 Dec 2025 11:06 Actions
3282 Project progress work New Normal [Coding] PO Stock Order FIX Lux Aubon 0.00 13 Dec 2025 11:05 Actions
3281 Project progress work New Normal [Coding] PO Order FIX Lux Aubon 0.00 13 Dec 2025 11:04 Actions
3280 Project progress work New Normal [Installation&On-site support] Go live Soraya Norasing 8.00 0.00 13 Dec 2025 10:11 Actions
3279 Project progress work New Normal [Installation&On-site support] Teaching for Go live Soraya Norasing 8.00 0.00 13 Dec 2025 10:10 Actions
3278 Project progress work New Normal [Installation&On-site support] Supports user feedback Soraya Norasing 24.00 0.00 13 Dec 2025 10:09 Actions
3277 Project progress work New Normal [Installation&On-site support] User Testing & Trial Soraya Norasing 24.00 0.00 13 Dec 2025 10:08 Actions
3276 Project progress work New Normal [Installation&On-site support] Teaching for UT (Shift B) Soraya Norasing 8.00 0.00 13 Dec 2025 10:07 Actions
3275 Project progress work New Normal [Installation&On-site support] Teaching for UT (Shift A) Soraya Norasing 8.00 0.00 13 Dec 2025 10:06 Actions
3274 Project progress work New Normal Software installation [Taping Label System] Soraya Norasing 24.00 0.00 13 Dec 2025 10:05 Actions
3273 Project progress work New Normal [Installation&On-site support] Go live Soraya Norasing 8.00 0.00 13 Dec 2025 10:03 Actions
3272 Project progress work New Normal [Installation&On-site support] Teaching for Go live Soraya Norasing 8.00 0.00 13 Dec 2025 10:01 Actions
3271 Project progress work New Normal [Installation&On-site support] Supports user feedback Soraya Norasing 32.00 0.00 13 Dec 2025 10:00 Actions
(26-50/627) Per page: 25, 50, 100