open[PJ260116] Modify Guide for Conveyor test room D-Line
Updated by Waraporn Promsopa about 1 hour ago
1 Mechanical cost
1-1 1. Guide for Replacement at Drive Unit Qty 1 set
2 Engineering cost
2-1 Concept Design / Spec. Meeting Qty 1 set
3 Installation and Commissioning
3-1 Installation and Commissioning Qty 1 job
Job Scope for Modification Guide Drive Unit
- Move Existing Module Test (3 Module) by A-Frame
- Modify Cutting & Dismantle Old Guide Drive Unit by Hot Work
- Install New Guide Drive Unit by welding
- Return Existing Module Test (3 Module) by A-Frame
- Test Run and Machine Commistioning
Include :
Transportation and Tool
Safety check and Quality check
Stand By Production 3 Days (1 Shift : 08.00-21.00)
Note)
Condition : This Quotation for Dismantle and Installation new guide at drive unit only
Delivery : 3-4 Weeks or by Disucssion
Validity : 30 Days
1). MCP provide Handlift x2 Set
2). MCP provide Operator for support test
3). Job Duration 3 Days ( Fri-Night ,Sat and Sun )
Remark:
50% DP upon PO
40% after Finished installation
10% after Finished handover