Estimated time: 19438.00 Spent time: 5453.00

# Tracker Status Priority Subject Assignee Total estimated time Total spent time Updated
1300 Project progress work In Progress Normal [Coding] Suphawat Tinaso 136.00 8.00 30 Mar 2026 13:19 Actions
1298 Project progress work New Normal [Requirement definition] Nattapol Poeam 64.00 0.00 04 Sep 2025 14:42 Actions
1289 Parent project In Progress Normal [PJ250052] Infrastructure IoT system for NTN Manufacturing(Thailand) NTPT Nattapol Poeam 416.00 64.00 30 Mar 2026 13:19 Actions
1288 Project progress work In Progress Normal [Installation&On-site support] Software installation 752.00 0.00 11 Mar 2026 10:50 Actions
1287 Project progress work In Progress Normal [Coding] Web application Worawit Khantamool 176.00 0.00 08 Apr 2026 10:47 Actions
1284 Parent project In Progress Normal [PJ250039] Infrastructure IoT system for Thai Asahi Denso Nattapol Poeam 2880.00 80.00 08 Apr 2026 10:47 Actions
1244 Parent project In Progress Normal [PJ250047] Process control system project modification report 10% Soraya Norasing 96.00 0.00 19 Jan 2026 14:24 Actions
1229 Sales support New Normal Palletizer - Kao (Concept) Warit Chunlaka 80.00 0.00 22 Aug 2025 15:13 Actions
1228 Project progress work New Normal Palletizer - JCU (Concept) Warit Chunlaka 0.00 22 Aug 2025 14:45 Actions
1227 Project progress work Confirmation request Normal Estimate cost for Thai Yokorei (DAIFUKU) Warit Chunlaka 4.00 22 Aug 2025 15:01 Actions
1226 Project progress work Confirmation request Normal Estimate cost for DAIFUKU - PCG WET4 Warit Chunlaka 24.00 4.00 22 Aug 2025 14:58 Actions
1223 Project progress work New Normal [Requirement definition] Warit Chunlaka 104.00 8.00 22 Aug 2025 15:13 Actions
1216 Project progress work New Normal Appointment to Survey and Summary final data Nattawat Hannok 16.00 0.00 21 Aug 2025 15:29 Actions
1215 Project progress work New Normal Sent the list to Ryo san choose Nattawat Hannok 24.00 8.00 21 Aug 2025 15:29 Actions
1214 Project progress work New Normal Find WH and making list Nattawat Hannok 8.00 8.00 21 Aug 2025 15:19 Actions
1213 Project progress work New Normal Spec meeting Robot Palletizer (Kao) Warit Chunlaka 0.00 21 Aug 2025 14:44 Actions
1212 Project progress work New Normal Second hand Robot ( JCU - Palletizer ) Warit Chunlaka 0.00 21 Aug 2025 14:44 Actions
1211 Project progress work In Progress Normal Rental Warehouse Warit Chunlaka 32.00 16.00 21 Aug 2025 15:29 Actions
1210 Project progress work New Normal Standard for ME-Drawing Template / Parts list format Warit Chunlaka 104.00 16.00 21 Aug 2025 14:16 Actions
1209 Project progress work Confirmation request Normal Estimate cost for Thai Yokorei (DAIFUKU) Warit Chunlaka 8.00 4.00 22 Aug 2025 14:37 Actions
1184 Project progress work In Progress Normal [Coding] Software development (Web) Ronnagon Kongsuwan 360.00 0.00 05 Mar 2026 16:27 Actions
1174 Project progress work In Progress Normal [Installation&On-site support] Priroj Neamjarn 944.00 0.00 23 Mar 2026 16:26 Actions
1173 Project progress work New Normal [Coding] Priroj Neamjarn 1152.00 0.00 30 Apr 2026 15:07 Actions
1166 Project progress work In Progress Normal [Coding] Schedule 508.00 153.00 18 Mar 2026 14:53 Actions
1165 Project progress work In Progress Normal [Internal Design] Kittisak Isarapongporn 40.00 0.00 06 Mar 2026 16:02 Actions
(401-425/520) Per page: 25, 50, 100