Project

General

Profile

Activity

From 12 Dec 2023 to 21 Dec 2023

21 Dec 2023

16:56 ATA Casting Technology Co., Ltd. 8.00 hours (Project progress work #322 (Closed): Insert data part NG packageing at QC )
Finish Santi Srichankaew
16:49 Pandora Production Co., Ltd. 8.00 hours (Project progress work #329 (Closed): Install equipment in the small box.)
Suchin Viyasing
16:47 Shodensha (Thailand) Co., Ltd. 8.00 hours (Project progress work #324 (Closed): Checkru the output settings in cells in an Excel sheet.)
Develop the output settings in cells in an Excel sheet. Kamol Anekchatnuntakool
16:43 Minebea AccessSolutions Thai Ltd 4.00 hours (Project progress work #98 (Closed): [Coding]PHP Pegasus web function)
Programming the backend API Kittisak Isarapongporn
16:42 ACME INDUSTRY CO.,LTD. 4.00 hours (Project progress work #204 (Closed): UAT about the WMS system and onsite support)
Update manual document for Handy revision 4 and migrate the system to production server Kittisak Isarapongporn
16:40 ACME INDUSTRY CO.,LTD. 8.00 hours (Project progress work #51 (Closed): Overall project development for web and handy)
Modify handy application added 4 functions and issue new release version 1.1.8 Kittisak Isarapongporn
08:08 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #323 (Closed): Design equipment in the cabinet)
Design drawing Suchin Viyasing

20 Dec 2023

19:32 Shodensha (Thailand) Co., Ltd. 8.00 hours (Project progress work #324 (Closed): Checkru the output settings in cells in an Excel sheet.)
Develop the output settings in cells in an Excel sheet. Kamol Anekchatnuntakool
19:11 Minebea AccessSolutions Thai Ltd 8.00 hours (Project progress work #97 (Closed): [Coding]Android handyterminal BTA500)
Soraya Norasing
15:33 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #323 (Closed): Design equipment in the cabinet)
Design drawing Suchin Viyasing
00:09 Minebea AccessSolutions Thai Ltd 8.00 hours (Project progress work #98 (Closed): [Coding]PHP Pegasus web function)
Kittisak Isarapongporn

19 Dec 2023

23:05 Minebea AccessSolutions Thai Ltd 4.00 hours (Project progress work #97 (Closed): [Coding]Android handyterminal BTA500)
Soraya Norasing
21:44 Ueda Plastic (Thailand) Co.,Ltd. 1.00 hour (Project progress work #327 (Closed): Sales label for ueda)
Create document and derivery Ryo Nozaki
21:41 Tomas Tech Co.,Ltd. 4.00 hours (Sales support #24 (Closed): [FY2023]Common management for Ryo Nozaki)
Summrize document Ryo Nozaki
21:40 Thai Honda Manufacturing Co., Ltd 4.00 hours (Sales support #237 (Closed): Make proposal for IoT system)
Meeting with CPO and GM staff Ryo Nozaki
21:37 DENSO Philippines Corporation 4.00 hours (Project progress work #22 (Closed): Make specification document for project)
Meeting with KDDI Ryo Nozaki
21:36 JTEKT MACHINE SYSTEMS (THAILAND) CO., LTD. 4.00 hours (Sales support #326 (Closed): Proposal IoT system for production line)
Site survery and meeting Ryo Nozaki
16:56 Asian Stanley. International Limited 4.00 hours (Project progress work #325 (Closed): Test the report)
Soraya Norasing
16:48 Shodensha (Thailand) Co., Ltd. 3.00 hours (Project progress work #324 (Closed): Checkru the output settings in cells in an Excel sheet.)
Check and Design the output settings in cells in an Excel sheet. Kamol Anekchatnuntakool
16:42 ATA Casting Technology Co., Ltd. 5.00 hours (Project progress work #310 (Closed): Support config Data Master Reader and insert Data Laser.)
Support insert Data Assembly 3 Pallet. Kamol Anekchatnuntakool
08:18 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #124 (Closed): [Installation&On-site support] Production IoT system for JATH)
Deverlop PLC calculate bekido function LINE LINK PRODUCTION 20% Santi Srichankaew
08:17 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #124 (Closed): [Installation&On-site support] Production IoT system for JATH)
Deverlop PLC calculate bekido function LINE LINK PRODUCTION 20% Santi Srichankaew
08:17 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #124 (Closed): [Installation&On-site support] Production IoT system for JATH)
Deverlop PLC calculate bekido function LINE LINK PRODUCTION 20% Santi Srichankaew
08:17 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #124 (Closed): [Installation&On-site support] Production IoT system for JATH)
Deverlop PLC calculate bekido function LINE LINK PRODUCTION 20% Santi Srichankaew
08:02 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #321 (Closed): Design equipment in the cabinet)
Design drawing Suchin Viyasing

18 Dec 2023

23:51 ACME INDUSTRY CO.,LTD. 8.00 hours (Project progress work #204 (Closed): UAT about the WMS system and onsite support)
On-site support and check the files that user needs to import Kittisak Isarapongporn
23:11 Minebea AccessSolutions Thai Ltd 8.00 hours (Project progress work #97 (Closed): [Coding]Android handyterminal BTA500)
Soraya Norasing
20:18 ATA Casting Technology Co., Ltd. 8.00 hours (Project progress work #310 (Closed): Support config Data Master Reader and insert Data Laser.)
Support insert Data Laser 3 Pallet and Data Assembly 3 Pallet. Kamol Anekchatnuntakool
17:15 Tomas Tech Co.,Ltd. 8.00 hours (Project progress work #308 (Closed): Review and learn the source code of the project.)
Tanawan Wongsa-ard
13:24 NTPT Company Limited. 2.00 hours (Project progress work #49 (Closed): ConMas i-Reporter tablet quote 43sets)
Meeting with K.Usui Ryo Nozaki
13:23 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 4.00 hours (Sales support #320 (Closed): ConMas i-Reporter proposal for JATH)
JATH meeting with i-Reporter Ryo Nozaki
13:19 Tomas Tech Co.,Ltd. 2.00 hours (Sales support #319 (Closed): KU Nomura meeting about Sekiden proposal for MRP system)
Meeting with KU Nomura Ryo Nozaki
13:17 Tomas Tech Co.,Ltd. 2.00 hours (Sales support #318 (Closed): Okaya meeting with Cimtops and Morioka about i-Reporter)
Meeting at Okaya office Ryo Nozaki
13:14 SANKO MOLD AND PLASTICS (THAILAND) COMPANY LIMITED. 4.00 hours (Project progress work #317 (Closed): Greeting meeting with Mr.Nakashima)
Greeting meeting with Nakashima MD Ryo Nozaki
13:12 IIDA SEIMITSU (THAILAND) CO., LTD. 4.00 hours (Sales support #282 (Closed): Proposal IoT system for production line)
Site survery and sumarize wiring cost for customer Ryo Nozaki

15 Dec 2023

22:22 ACME INDUSTRY CO.,LTD. 8.00 hours (Project progress work #204 (Closed): UAT about the WMS system and onsite support)
Modify the store proc about the schedule generator and support user for the testing Kittisak Isarapongporn
17:45 ATA Casting Technology Co., Ltd. 8.00 hours (Project progress work #310 (Closed): Support config Data Master Reader and insert Data Laser.)
Support config Data Master Reader and insert Data Laser. Kamol Anekchatnuntakool
17:41 Minebea AccessSolutions Thai Ltd 8.00 hours (Project progress work #97 (Closed): [Coding]Android handyterminal BTA500)
Soraya Norasing
17:30 Tomas Tech Co.,Ltd. 8.00 hours (Project progress work #308 (Closed): Review and learn the source code of the project.)
Tanawan Wongsa-ard
16:51 Tomas Tech Co.,Ltd. 8.00 hours (Project progress work #308 (Closed): Review and learn the source code of the project.)
Tanawan Wongsa-ard
10:56 Tomas Tech Co.,Ltd. 8.00 hours (Project progress work #308 (Closed): Review and learn the source code of the project.)
Tanawan Wongsa-ard
10:55 Tomas Tech Co.,Ltd. 8.00 hours (Project progress work #308 (Closed): Review and learn the source code of the project.)
Tanawan Wongsa-ard
16:30 Thai Nippon foods Co.,Ltd. 8.00 hours (Project progress work #297 (Closed): Wiring cable in the cabinet)
Design drawing Jtekt Suchin Viyasing

14 Dec 2023

22:07 Minebea AccessSolutions Thai Ltd 8.00 hours (Project progress work #299 (Closed): Modify the specification document and confirm the design)
Kittisak Isarapongporn
17:30 Minebea AccessSolutions Thai Ltd 8.00 hours (Project progress work #97 (Closed): [Coding]Android handyterminal BTA500)
Soraya Norasing
16:51 A.N.I. LOGISTICS, LTD. 8.00 hours (Project progress work #130 (Closed): [Coding]Inner packing screen function C#)
Develop Inner packing screen function C#. Kamol Anekchatnuntakool
16:29 Thai Nippon foods Co.,Ltd. 8.00 hours (Project progress work #297 (Closed): Wiring cable in the cabinet)
Wiring cable in the cabinet Suchin Viyasing
11:51 ADVICS Manufacturing(Thailand)Co.,Ltd. 4.00 hours (Project progress work #307 (Closed): Installation FTP On server data from PLC Bekido)
Installation FTP On server data from PLC Bekido Santi Srichankaew
11:50 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 4.00 hours (Project progress work #306 (Closed): Meeting Kick off IOT bekido and OA monitoring #2)
Bekido monitoring Santi Srichankaew

13 Dec 2023

23:51 FTS AUTOMOTIVE (THAILAND) CO.,LTD 1.00 hour (Sales support #231 (Closed): Replace procejet from D100 to KV8000 and XD02)
Contenue proposal and customer said set budjet at April 2024 Ryo Nozaki
23:50 Mitsubishi Heavy Industries-Mahajak Air Conditioners Co., Ltd 1.00 hour (Project progress work #213 (Closed): Proposal IoT system for Maco production line)
Handover to K.Boy. The meeting will be booked on a separate ticket. Ryo Nozaki
23:49 EBARA FOODS (THAILAND) CO., LTD. 1.00 hour (Sales support #61 (Closed): Proposal activities + proposal document creation)
Lost , customer choose other vender from Japan Ryo Nozaki
23:49 ACME INDUSTRY CO.,LTD. 1.00 hour (Sales support #63 (Closed): IoT project Proposal activities + requirements definition)
Summrize proposal and explain Ms.Mukai Ryo Nozaki
23:48 A.N.I. LOGISTICS, LTD. 1.00 hour (Sales support #62 (Closed): CKD project phase3 Proposal activities + requirements definition)
Handover to K.Nack. The meeting will be booked on a separate ticket. Ryo Nozaki
23:47 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 1.00 hour (Project progress work #143 (Closed): Production IoT project requirements and support project)
Crate and conteniue management other ticket Ryo Nozaki
23:45 Minebea AccessSolutions Thai Ltd 2.00 hours (Project progress work #10 (Closed): Creating a specification document)
Inernal meeting and sumrize document Ryo Nozaki
23:34 Tomas Tech Co.,Ltd. 4.00 hours (Sales support #305 (Closed): Aisan industry meeting with Mr.Inagaki and keyence Eyama)
Ryo Nozaki
23:33 Tomas Tech Co.,Ltd. 4.00 hours (Project progress work #304 (Closed): OTICS (Thailand) Company Limited sales for IoT system)
Meeting with Mr.Matsuura Ryo Nozaki
23:30 Nissan Motor (Thailand) Co., Ltd. 2.00 hours (Sales support #89 (Closed): New OCR project for Fac1 and Fac2)
Lost Ryo Nozaki
23:29 Minebea AccessSolutions Thai Ltd 2.00 hours (Project progress work #303 (Closed): [Requirement definition] Handy terminal stock management system for Pegasus for MAS-T)
Meeting with Thai menber at MAS-T Ryo Nozaki
23:26 Tomas Tech Co.,Ltd. 2.00 hours (Sales support #302 (Closed): YAMASA ASIA OCEANIA CO., LTD. meeting about sales)
Meeting with Mr.Kanuma Ryo Nozaki
23:25 Tomas Tech Co.,Ltd. 2.00 hours (Project progress work #301 (Closed): Keyence Mr.Shima meeting about New WD IoT demo unit and HRX100-300-500)
Meeting with Mr.Shima Ryo Nozaki
20:59 Minebea AccessSolutions Thai Ltd 6.00 hours (Project progress work #97 (Closed): [Coding]Android handyterminal BTA500)
Soraya Norasing
20:57 Tomas Tech Co.,Ltd. 1.00 hour (Sales support #20 (Closed): [FY2023]Common management for Soraya)
Soraya Norasing
20:53 Nidec Techno Motor (Thailand) Co.,Ltd. 1.00 hour (Project progress work #198 (Closed): HTA_NSET modification completion label function)
Soraya Norasing
17:16 Thai Nippon foods Co.,Ltd. 8.00 hours (Project progress work #268 (Closed): Making control cabinet wiring 4set )
Wiring cable in the cabinet Suchin Viyasing
16:46 Thai Nippon foods Co.,Ltd. 8.00 hours (Project progress work #297 (Closed): Wiring cable in the cabinet)
wiring in the 4th control cabinet. Suchin Viyasing
16:45 A.N.I. LOGISTICS, LTD. 8.00 hours (Project progress work #130 (Closed): [Coding]Inner packing screen function C#)
Develop Inner packing screen function C#. Kamol Anekchatnuntakool
16:22 Minebea AccessSolutions Thai Ltd 2.00 hours (Project progress work #299 (Closed): Modify the specification document and confirm the design)
Update TO-DO list Kittisak Isarapongporn
16:21 Ebisu Foods Co Ltd. 1.00 hour (Project progress work #300 (Closed): Weekly meeting (Wed 15.00-16.00pm))
Kittisak Isarapongporn
16:12 A.N.I. LOGISTICS, LTD. 5.00 hours (Project progress work #226 (Closed): CKD project requirement and document preparation)
Modify spec and weekly meeting Kittisak Isarapongporn

12 Dec 2023

21:37 ACME INDUSTRY CO.,LTD. 2.00 hours (Project progress work #204 (Closed): UAT about the WMS system and onsite support)
Import the master data for SUB ASSY and CAVITY items. Kittisak Isarapongporn
21:11 ACME INDUSTRY CO.,LTD. 4.00 hours (Project progress work #204 (Closed): UAT about the WMS system and onsite support)
Teaching about schedule operation for Injection staff Kittisak Isarapongporn
21:32 Minebea AccessSolutions Thai Ltd 6.00 hours (Project progress work #299 (Closed): Modify the specification document and confirm the design)
Kittisak Isarapongporn
17:32 Nidec Techno Motor (Thailand) Co.,Ltd. 8.00 hours (Project progress work #298 (Closed): Modify the functionality of the Direct Labor)
Soraya Norasing
16:59 Thai Nippon foods Co.,Ltd. 8.00 hours (Project progress work #297 (Closed): Wiring cable in the cabinet)
Suchin Viyasing
16:45 A.N.I. LOGISTICS, LTD. 8.00 hours (Project progress work #130 (Closed): [Coding]Inner packing screen function C#)
Develop Inner packing screen function C#. Kamol Anekchatnuntakool
 