- 17:46 Nidec Techno Motor (Thailand) Co.,Ltd. Problem-Bug #138 (Confirmation request): HTA_NSET completion fix bug.
- “Problem”
1.)The slip can be printed even if the qty is incomplete. Normally it must be unprintable.
2.)Adjust scr... - 13:41 Nidec Techno Motor (Thailand) Co.,Ltd. Problem-Bug #138 (In Progress): HTA_NSET completion fix bug.
- 13:41 Nidec Techno Motor (Thailand) Co.,Ltd. Problem-Bug #138 (Closed): HTA_NSET completion fix bug.
- List of bugs as reported by the customer in the attached file.
- 15:36 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. Project progress work #141 (Closed): [Task]Deverlop HMI Bekido and OA monitoring
- Deverlop HMI Bekido and OA monitoring
PLC creat program - 15:33 ADVICS Manufacturing(Thailand)Co.,Ltd. Sales support #140 (Closed): IOT Monitoring
- -Alarm CNC monitoring mo FANUC
-Concept IOT - 15:31 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. Sales support #139 (Closed): Meeting Kick off IOT bekido and OA monitoring
- -Scope of work
-Part support
-Schedule work flow
-HMI monitor viewer
-Layout plants
Next metting
24/10/2023 ... - 15:29 Shodensha (Thailand) Co., Ltd. Problem-Bug #60 (Confirmation request): Procedure manual application development modifictaion problem
- I revise Manual Software finish krub.
- 13:38 Asian Stanley. International Limited Project progress work #59: Support installation HT-Label printing system
- [20/10/23]
-setup handy and install application on handy
-test printing label form handy to printer server. and fo... - 12:41 Asian Stanley. International Limited Problem-Bug #73: Found 500 return error
- Fixed error
1. set time interval load data every 30 second.
2. add script auto refresh page if have error code 500.... - 09:31 Mitsui Precision Thai Co.,Ltd Sales support #137 (Closed): Sales and presentation about Pegasus production management system
- 08:44 SANKO MOLD AND PLASTICS (THAILAND) COMPANY LIMITED. Project progress work #136 (Closed): Install function Cancel inbound and outbound
- 24 Oct 2023
I will install function Cancel inbound and outbound
Today K.Oh holiday krub.
20 Oct 2023
- 18:36 Ebisu Foods Co Ltd. Project progress work #17: WMS handy terminal BT-A500 coding with Java Android.
- Today: Development edit Stock Check
Tomorrow: Development Stock Adjusment - 17:22 SANKO MOLD AND PLASTICS (THAILAND) COMPANY LIMITED. Project progress work #50 (Close request): Add delete function
- 08:14 SANKO MOLD AND PLASTICS (THAILAND) COMPANY LIMITED. Project progress work #50 (Confirmation request): Add delete function
- function cancel outbound pegasus completed
change design inbound
add function cancel inbound
update stack after ... - 16:14 Shodensha (Thailand) Co., Ltd. Problem-Bug #60: Procedure manual application development modifictaion problem
- Revise manual application krub.
- 09:54 Shodensha (Thailand) Co., Ltd. Problem-Bug #60 (In Progress): Procedure manual application development modifictaion problem
- Revise manual application krub.
- 07:40 Asian Stanley. International Limited Project progress work #8: Support installation for power supply and LAN cable for 50 points
- 19/10/2023
- The power distribution cabinet and lag hub cabinet have been installed and connected to the Network.
-...
19 Oct 2023
- 21:59 PANASONIC AUTOMOTIVE SYSTEMS ASIA PACIFIC CO.,LTD. Sales support #67 (In Progress): Automatic label pasting machine Concept proposal
- - Material Received Data
- RFID equipment spec - 21:55 Tomas Tech Co.,Ltd. Sales support #30 (In Progress): [FY2023]Common management for Nattapol
- 21:49 MURATA(THAILAND)CO.,LTD. Sales support #40: Install PTL System at OfficeMate Suvinthawong
- Quotation from SND Rev.2
- 21:45 Tomas Tech Co.,Ltd. Sales support #45: PTL DEMO kit concept for murata
- Quote from ATT Rev.1
- 14:58 Tomas Tech Co.,Ltd. Sales support #45: PTL DEMO kit concept for murata
- Update Concept PTL picking Cart Rev.1
- 20:57 Asian Stanley. International Limited Project progress work #59: Support installation HT-Label printing system
- - Set up IP printer and test printing via server.
- 20:51 Asian Stanley. International Limited Project progress work #59 (In Progress): Support installation HT-Label printing system
- 20:47 A.N.I. LOGISTICS, LTD. Problem-Bug #135 (Close request): The power went off
- 20:46 A.N.I. LOGISTICS, LTD. Problem-Bug #135 (Closed): The power went off
- Support to restart the system and checking
- 20:40 Ebisu Foods Co Ltd. Project progress work #17: WMS handy terminal BT-A500 coding with Java Android.
- Today: Development Stock Check
Tomorrow: Development edit Stock Check - 18:10 Tomas Tech Co.,Ltd. Project progress work #35 (Close request): PLC alarm record and send to line notify
- 14:04 Tomas Tech Co.,Ltd. Project progress work #35 (Confirmation request): PLC alarm record and send to line notify
- Develop Software send picture from PLC to line notify OK krub.
- 14:55 ATA Casting Technology Co., Ltd. Problem-Bug #56: Packing system no need scan pallet no
- Add Source Code krub.
- 10:17 ATA Casting Technology Co., Ltd. Problem-Bug #56 (Close request): Packing system no need scan pallet no
- 07:58 ATA Casting Technology Co., Ltd. Problem-Bug #56 (Confirmation request): Packing system no need scan pallet no
- 14:30 Asteer (Thailand) Co., Ltd. Project progress work #21: Handy terminal application system Development.
- Change due date to 10/24/2023 because I revise software Shodensha 10/20/2023 - 10/21/2023 krub.
- 09:20 Asteer (Thailand) Co., Ltd. Project progress work #21: Handy terminal application system Development.
- Develop HT send data to PLC.
- 12:47 A.N.I. LOGISTICS, LTD. Project progress work #134 (Closed): [Installation&On-site support] CKD process management system phase3 for ANI
- 12:47 A.N.I. LOGISTICS, LTD. Project progress work #133 (Closed): [Installation&On-site support] CKD process management system phase3 for ANI
- 12:47 A.N.I. LOGISTICS, LTD. Project progress work #132 (Closed): [Installation&On-site support] CKD process management system phase3 for ANI
- 12:39 A.N.I. LOGISTICS, LTD. Project progress work #131 (Closed): [Coding]Android handy and tablet modification Java
- 12:38 A.N.I. LOGISTICS, LTD. Project progress work #130 (Closed): [Coding]Inner packing screen function C#
- 12:37 A.N.I. LOGISTICS, LTD. Project progress work #129 (Interruption): [Coding]PHP Pegasus web function
- 12:37 A.N.I. LOGISTICS, LTD. Project progress work #128 (Closed): [Internal Design] DB and various functions, man-hour calculation
- 12:35 A.N.I. LOGISTICS, LTD. Problem-Bug #58 (Closed): [CKD Pegasus system phase 1&2]Packing data not found error on Handy and Tablet in outer packing area
- 10:11 A.N.I. LOGISTICS, LTD. Problem-Bug #58 (Close request): [CKD Pegasus system phase 1&2]Packing data not found error on Handy and Tablet in outer packing area
- 12:32 Thai Nippon foods Co.,Ltd. Project progress work #127 (Closed): [Installation&On-site support] Production IoT system for TNF
- 12:32 Thai Nippon foods Co.,Ltd. Project progress work #126 (Closed): [Installation&On-site support] Production IoT system for TNF
- 12:31 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. Project progress work #125 (Closed): [Installation&On-site support] Production IoT system for JATH
- 12:29 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. Project progress work #124 (Closed): [Installation&On-site support] Production IoT system for JATH
- 12:29 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. Project progress work #123 (Closed): [Installation&On-site support] Production IoT system for JATH
- 12:24 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. Project progress work #122 (Closed): [Coding&UT] PHP web function
- 12:23 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. Project progress work #121 (Closed): [Coding&UT] PLC and DB linkage function
- 12:22 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. Project progress work #120 (Closed): [Coding&UT] KV8000 Touch display and XD02 monitor screen
- 12:21 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. Project progress work #119 (Closed): [Internal Design] DB and various functions, man-hour calculation
- 12:07 DENSO Philippines Corporation Project progress work #118 (Closed): [Installation]Link with smart device and PHP web Data reference, graph creation, scan Kanban registration functions at Philippines
- 12:06 DENSO Philippines Corporation Project progress work #117 (Closed): [Installation]Link with smart device and PHP web Data reference, graph creation, scan Kanban registration functions at Philippines
- 12:06 DENSO Philippines Corporation Project progress work #116 (Closed): [System Testing]Link with smart device and PHP web Data reference, graph creation, scan Kanban registration functions
- 12:05 DENSO Philippines Corporation Project progress work #115 (Closed): [System Testing]Link with smart device and PHP web Data reference, graph creation, scan Kanban registration functions
- 12:05 DENSO Philippines Corporation Project progress work #114 (Closed): [System Testing]Link with smart device and PHP web Data reference, graph creation, scan Kanban registration functions
- 12:04 DENSO Philippines Corporation Project progress work #113 (Closed): [Coding]PHP web Data reference, graph creation, scan Kanban registration functions Phase01
- 12:02 DENSO Philippines Corporation Project progress work #112 (Closed): [Coding]Android smart watch , smart phone , Data linkage function Phase01
- 12:01 DENSO Philippines Corporation Project progress work #111 (Closed): [Internal Design] DB and various functions, man-hour calculation
- 11:59 Asteer (Thailand) Co., Ltd. Project progress work #110 (Closed): [On-site support]Support after cutover
- 11:59 Asteer (Thailand) Co., Ltd. Project progress work #109 (Closed): [On-site support]Support after cutover
- 11:55 Ebisu Foods Co Ltd. Project progress work #108 (Closed): [Installation&On-site support]Project Warehouse management system for Ebisu
- 11:55 Ebisu Foods Co Ltd. Project progress work #107 (Closed): [Installation&On-site support]Project Warehouse management system for Ebisu
- 11:50 Minebea AccessSolutions Thai Ltd Project progress work #106 (Closed): [System Testing]ST with AS400
- 11:49 Minebea AccessSolutions Thai Ltd Project progress work #105 (Closed): [Coding]Data linkage function
- 11:47 Minebea AccessSolutions Thai Ltd Project progress work #104 (Closed): [Installation&On-site support]Project Stock management system for MAS-T
- 11:47 Minebea AccessSolutions Thai Ltd Project progress work #103 (Closed): [Installation&On-site support]Project Stock management system for MAS-T
- 11:47 Minebea AccessSolutions Thai Ltd Project progress work #102 (Closed): [Installation&On-site support]Project Stock management system for MAS-T
- 11:44 Minebea AccessSolutions Thai Ltd Project progress work #101 (Closed): [System Testing]Handyterminal and Web
- 11:43 Minebea AccessSolutions Thai Ltd Project progress work #100 (Closed): [System Testing]Handyterminal and Web
- 11:42 Minebea AccessSolutions Thai Ltd Project progress work #99 (Closed): [System Testing]Handyterminal and Web
- 11:42 Minebea AccessSolutions Thai Ltd Project progress work #98 (Closed): [Coding]PHP Pegasus web function
- 11:39 Minebea AccessSolutions Thai Ltd Project progress work #97 (Closed): [Coding]Android handyterminal BTA500
- 11:38 Minebea AccessSolutions Thai Ltd Project progress work #96 (Closed): [Internal Design] DB and various functions, man-hour calculation
- 11:35 Asian Stanley. International Limited Project progress work #95 (Closed): Support installation for power supply and LAN cable for 20 points
- Support installation for power supply and LAN cable for 20 points
- Control and coordinate between wiring or LAN ins... - 11:29 ACME INDUSTRY CO.,LTD. Project progress work #94 (Closed): [On-site support]Support after cutover
- 11:29 ACME INDUSTRY CO.,LTD. Project progress work #93 (Interruption): [On-site support]Support after cutover
- 11:28 ACME INDUSTRY CO.,LTD. Project progress work #92 (Closed): [On-site support]Support after cutover
- 11:20 ADVICS Manufacturing(Thailand)Co.,Ltd. Project progress work #12: Addition function display
- Update program complate
Wait customer comments - 10:17 Nidec Techno Motor (Thailand) Co.,Ltd. Project progress work #47 (Close request): create spectification document
- 09:49 Asteer (Thailand) Co., Ltd. Project progress work #38: Devolop and debug PLC Mitsubishi Q Series
- Deverlop PLC Keyencce test OK/NG data sendingnormal
next step
Deverlop to PLC Mitsubishi waiting demo PLC Mitsubi... - 08:25 Ebisu Foods Co Ltd. Project progress work #16: WMS Web Development
Today
Waiting Team SAP Ebisu send API Link Sales Order to me
- 08:10 SANKO MOLD AND PLASTICS (THAILAND) COMPANY LIMITED. Project progress work #50: Add delete function
- Today
change design Outbound
add function cancel Outbound
update stack after cancel Outbound
calculate stock c... - 08:07 Asian Stanley. International Limited Problem-Bug #73 (In Progress): Found 500 return error
- Today I will Monitor by remote Anydesk
- 08:05 ATA Casting Technology Co., Ltd. Project progress work #91 (Closed): Modify Pegasus.
- The customer has requested to modify the search for the number of Pallet digits from 9 to 14 for Pegasus.
18 Oct 2023
- 21:06 MURATA(THAILAND)CO.,LTD. Sales support #40 (In Progress): Install PTL System at OfficeMate Suvinthawong
- 21:04 MURATA(THAILAND)CO.,LTD. Sales support #40 (New): Install PTL System at OfficeMate Suvinthawong
- 08:23 MURATA(THAILAND)CO.,LTD. Sales support #40: Install PTL System at OfficeMate Suvinthawong
- Wait SND team sent new Quotation for add price HUB and rack
- 20:43 A.N.I. LOGISTICS, LTD. Sales support #62 (In Progress): CKD project phase3 Proposal activities + requirements definition
- 18:57 A.N.I. LOGISTICS, LTD. Sales support #62 (Closed): CKD project phase3 Proposal activities + requirements definition
- CKD project phase3 Proposal activities + requirements definition
Schedule : Pre-kick off meeting with Mr.Sakamoto ... - 20:39 Nissan Motor (Thailand) Co., Ltd. Problem-Bug #90 (Closed): Found the problem on HT02
- 20:37 Nissan Motor (Thailand) Co., Ltd. Sales support #89 (Closed): New OCR project for Fac1 and Fac2
- Handy terminal and plc for keyence concept
We will get po at Mid-Dec - 20:34 Nidec Techno Motor (Thailand) Co.,Ltd. Project progress work #88 (Closed): NSET - Compo detail (Add new slip)
- NSET - Compo detail (Add new slip)
Vietnamese will now test. - 20:33 Thai Nippon foods Co.,Ltd. Project progress work #87 (Closed): IoT Equipment for machine operation project
- 20:31 Thai Nippon foods Co.,Ltd. Sales support #86 (Closed): IoT Equipment for Water treatment project
- 20:14 Valeo Comfort and Driving Assistance Systems (Thailand) Limited Project progress work #85 (Closed): Scanner-PLC Data Convert suggetion
- 20:13 NTN Manufacturing(Thailand) Co., Ltd. Sales support #84 (Closed): NTN - iReporter suggetion
- Recheck the form on tablet
Wait for P - 20:12 ACME INDUSTRY CO.,LTD. Sales support #83 (Closed): PJ - line monitoring assembly & PJ- Machine operation monitoring Molding line
- IoT project
PJ - line monitoring assembly & pj - Machine operation monitoring Molding line - 20:10 NTPT Company Limited. Sales support #82 (Closed): NTPT - Warehouse system Proposal activities + requirements definition
- 20:09 NTPT Company Limited. Sales support #81 (Closed): NTPT - Documentation management Proposal activities + requirements definition
- NTPT - Documentation management
Proposal activities + requirements definition - 20:08 Tomas Tech Co.,Ltd. Sales support #80 (Closed): DPS operation training
- '- Application software
- Database structure
- Studying the SDMAT software (40%) - 20:06 Siam Denso Manufacturing Co.,Ltd. Sales support #79 (Closed): New line 23
- Waiting for PO
Already survey and estimate the price. - 20:06 Siam Denso Manufacturing Co.,Ltd. Problem-Bug #78 (Closed): Found problem about the alarm of sequnce
- Will enter site to solve the problem. 18th Nov
- 20:05 Siam Denso Manufacturing Co.,Ltd. Project progress work #77 (Closed): Data insertion test time
- K.Kamol is testing. Will confirm user for installation plan.
Waiting for file from user.
Will install after inserte... - 20:03 Nidec Techno Motor (Thailand) Co.,Ltd. Problem-Bug #76 (Closed): NSET - Reprint FG slip & Traceability system by Handy
- Found partail number exceed problem
Still can't reproduce the problem.
Add the logger in application and sent t... - 20:00 MAX(THAILAND)CO.,LTD. Problem-Bug #75 (Closed): Email function test
- 19:56 Asian Stanley. International Limited Problem-Bug #74 (Closed): Request to add 2 access points on the low signal area. Wiring is also need.
- Request to add 2 access points on the low signal area.
Wiring is also need.
Request quote from SND - 19:54 Asian Stanley. International Limited Problem-Bug #73 (Closed): Found 500 return error
- Can't reproduce the problem
Increase the memory allocate for PHP to 1GB - 19:51 Asian Stanley. International Limited Sales support #72 (Closed): Request the Windows server 2022 standard/ MSSQL2022 standard license
- Request the Windows server 2022 standard/ MSSQL2022 standard license
- 19:49 ATA Casting Technology Co., Ltd. Sales support #71 (In Progress): Machine operation monitoring
- Wait feedback from customer
- 19:48 ATA Casting Technology Co., Ltd. Sales support #71 (Closed): Machine operation monitoring
- 19:46 Kaneka (Thailand) Co., Ltd. Sales support #70 (In Progress): Kaneka - WMS pegasus Prepare quotation about M/A plan
- Wait for feedback from Kaneka
- 19:45 Kaneka (Thailand) Co., Ltd. Sales support #70 (Closed): Kaneka - WMS pegasus Prepare quotation about M/A plan
- Send quote for Kaneka
- 19:44 SIAM TRIX MANUFACTURING CO.,LTD. Sales support #69 (In Progress): Trix - Production planning software
- Wait for Japanese person on this Friday 11Aug
- 19:43 SIAM TRIX MANUFACTURING CO.,LTD. Sales support #69 (Closed): Trix - Production planning software
- 19:42 Ueda Plastic (Thailand) Co.,Ltd. Sales support #68 (Closed): User request to add the new function about stock check remaining
- 19:37 PANASONIC AUTOMOTIVE SYSTEMS ASIA PACIFIC CO.,LTD. Sales support #67 (Closed): Automatic label pasting machine Concept proposal
- 19:34 DAIFUKU (THAILAND) LTD. Project progress work #66 (Closed): [Area3]Camera control system
- 19:33 DAIFUKU (THAILAND) LTD. Project progress work #65 (Closed): [Area2]Camera control system
- 19:32 DAIFUKU (THAILAND) LTD. Project progress work #64 (Closed): [Area1]Camera control system
- 19:27 ACME INDUSTRY CO.,LTD. Sales support #63 (Closed): IoT project Proposal activities + requirements definition
- 19:11 Ebisu Foods Co Ltd. Project progress work #17: WMS handy terminal BT-A500 coding with Java Android.
- Today: Development faction Change Location
Tomorrow: Development Stock Check - 18:54 EBARA FOODS (THAILAND) CO., LTD. Sales support #61 (Closed): Proposal activities + proposal document creation
- Production management system proposal activities.
Requires linkage with accounting system. - 18:49 Shodensha (Thailand) Co., Ltd. Problem-Bug #60 (Closed): Procedure manual application development modifictaion problem
- 18:40 Asian Stanley. International Limited Project progress work #13 (Closed): Additional development of 4 screens
- 18:39 SANKO MOLD AND PLASTICS (THAILAND) COMPANY LIMITED. Project progress work #14 (Closed): Develop 4 additional functions
- 18:39 SANKO MOLD AND PLASTICS (THAILAND) COMPANY LIMITED. Problem-Bug #15 (Closed): SMTP handy terminal system malfunction
- 18:38 Tomas Tech Co.,Ltd. Project progress work #35 (In Progress): PLC alarm record and send to line notify
- please add source code file
- 18:37 Asian Stanley. International Limited Problem-Bug #37 (In Progress): UPS have problem
- This case is not yet closed.
Change the person in charge. We will take action by October 31st. - 18:35 Nidec Techno Motor (Thailand) Co.,Ltd. Project progress work #41 (Closed): ์ New condition
- 17:40 ATA Casting Technology Co., Ltd. Problem-Bug #56: Packing system no need scan pallet no
- The customer has requested to edit the search for the number of Pallet digits from 9 to 14 for Pegasus.
- 17:25 Asian Stanley. International Limited Project progress work #59 (Closed): Support installation HT-Label printing system
- -install and setup program on Handy, Server, Laptop, Printer.
-test printing label
-user training [program on handy... - 17:20 ADVICS Manufacturing(Thailand)Co.,Ltd. Project progress work #12: Addition function display
- Wait customer comment
- 17:10 Nidec Techno Motor (Thailand) Co.,Ltd. Project progress work #55: handy terminal BT-A500 coding with Java Android.
- Today: develop the functionality of the program page. And check database with customers, The customer created a new t...
- 14:34 A.N.I. LOGISTICS, LTD. Problem-Bug #58 (Closed): [CKD Pegasus system phase 1&2]Packing data not found error on Handy and Tablet in outer packing area
- Problem:
The tablet didn't show some packing list data. [Fixed]
The handy still found the problem. [In progress]
... - 14:01 ACME INDUSTRY CO.,LTD. Project progress work #54 (Interruption): Meeting about the pegasus
- 11:10 SANKO MOLD AND PLASTICS (THAILAND) COMPANY LIMITED. Project progress work #50 (In Progress): Add delete function
- change design inbound
add function cancel inbound
update stack after cancel inbound
calculate stock card record... - 11:02 Ebisu Foods Co Ltd. Project progress work #16: WMS Web Development
- Test report API sap to wms excerl
update create storeprocedure schedule waiting data form SAP and check trigger in... - 08:27 MURATA(THAILAND)CO.,LTD. Sales support #39: Install PTL System at food passion
- Sent new Quotation to K.Soravit and wait MURATA PO
- 08:17 Tomas Tech Co.,Ltd. Sales support #43: Install SR-X300S at Pandora
- Customer confirm install demo kit on station in next week
Buy small box for install power supply
17 Oct 2023
- 22:20 Ebisu Foods Co Ltd. Project progress work #17: WMS handy terminal BT-A500 coding with Java Android.
- Today: Development faction Stock Management
Tomorrow: Development API Stock Management - 20:17 Nidec Techno Motor (Thailand) Co.,Ltd. Project progress work #55 (In Progress): handy terminal BT-A500 coding with Java Android.
- Today: Design and adjust screen layout on Android Studio and check the functionality of the login page.
Tomorrow: St... - 15:33 Nidec Techno Motor (Thailand) Co.,Ltd. Project progress work #55 (Closed): handy terminal BT-A500 coding with Java Android.
- HTA_NSET app modification add Entranceexit management.
Implement handy terminal coding with Android Java. - 20:13 Nidec Techno Motor (Thailand) Co.,Ltd. Project progress work #47 (Confirmation request): create spectification document
- 20:11 Nidec Techno Motor (Thailand) Co.,Ltd. Project progress work #47 (In Progress): create spectification document
- The spectification document is finished.
Sent email with attachment to customer. - 15:26 Nidec Techno Motor (Thailand) Co.,Ltd. Project progress work #47: create spectification document
- create specification document done
- 19:58 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. Sales support #57 (Closed): Production IoT project requirements definition
- 19:56 ATA Casting Technology Co., Ltd. Problem-Bug #56 (Closed): Packing system no need scan pallet no
- Packing system no need scan pallet no
16 Oct 2023
- 17:44 Tomas Tech Co.,Ltd. Project progress work #35 (Close request): PLC alarm record and send to line notify
- 17:44 SANKO MOLD AND PLASTICS (THAILAND) COMPANY LIMITED. Problem-Bug #15 (Close request): SMTP handy terminal system malfunction
- 08:27 SANKO MOLD AND PLASTICS (THAILAND) COMPANY LIMITED. Problem-Bug #15 (Confirmation request): SMTP handy terminal system malfunction
- 17:44 SANKO MOLD AND PLASTICS (THAILAND) COMPANY LIMITED. Project progress work #14 (Close request): Develop 4 additional functions
- 07:57 SANKO MOLD AND PLASTICS (THAILAND) COMPANY LIMITED. Project progress work #14 (Confirmation request): Develop 4 additional functions
- Noted Krub
HT_SMPT.zip is coding Handdy
SMPT.zip is web pegasus - 17:44 Asian Stanley. International Limited Project progress work #13 (Close request): Additional development of 4 screens
- 08:20 Asian Stanley. International Limited Project progress work #13 (Confirmation request): Additional development of 4 screens
- last update screen
- 16:51 Asteer (Thailand) Co., Ltd. Project progress work #21: Handy terminal application system Development.
- Change Due date : 10/19/2023.
- 16:41 ACME INDUSTRY CO.,LTD. Project progress work #54 (Interruption): Meeting about the pegasus
- 16:40 ACME INDUSTRY CO.,LTD. Project progress work #53 (Closed): UAT about the WMS system
- :: Last updated: 2023-10-16
Present the current develop software of pegasus and handy. - 16:36 ACME INDUSTRY CO.,LTD. Project progress work #52 (Closed): Issue topics
- :: last updated: 2023-10-16
- Summarize the remaining topics and issues below.
1. Nisshin Ship & Air
- unit_qty... - 16:27 ACME INDUSTRY CO.,LTD. Project progress work #51 (Closed): Overall project development for web and handy
- ::2023-10-16
Development (Remaining topic/function)
+ Web
1. Overview report [Pending]
2. Tag Reprint [NEW] - s...
Also available in: Atom