Project

General

Profile

For internal project work assignment report without Nozaki

« December 2025 | February »

Apply Clear

Sunday Monday Tuesday Wednesday Thursday Friday Saturday
1

28

29

30

31

1

2

3

2

4

5

6

7

8

9

10

3

11

12

13

14

15

16

Project progress work #4448: [Installation&On-site support] Project progress work #4448: [Installation&On-site support]

Project: THAI YOKOREI CO., LTD.
Status: New
Start date: 16 Jan 2026
Due date:
Assignee:
Priority: Normal
Project progress work #4447: [Coding] Project progress work #4447: [Coding]

Project: THAI YOKOREI CO., LTD.
Status: New
Start date: 16 Jan 2026
Due date:
Assignee:
Priority: Normal
Project progress work #4446: [Internal Design] Project progress work #4446: [Internal Design]

Project: THAI YOKOREI CO., LTD.
Status: New
Start date: 16 Jan 2026
Due date:
Assignee:
Priority: Normal
Project progress work #4445: [Requirement definition] Project progress work #4445: [Requirement definition]

Project: THAI YOKOREI CO., LTD.
Status: New
Start date: 16 Jan 2026
Due date:
Assignee:
Priority: Normal
Project progress work #4444: [Installation&On-site support] Project progress work #4444: [Installation&On-site support]

Project: THAI YOKOREI CO., LTD.
Status: New
Start date: 16 Jan 2026
Due date:
Assignee:
Priority: Normal
Project progress work #4443: [Coding] Project progress work #4443: [Coding]

Project: THAI YOKOREI CO., LTD.
Status: New
Start date: 16 Jan 2026
Due date:
Assignee:
Priority: Normal
Project progress work #4442: [Internal Design] Project progress work #4442: [Internal Design]

Project: THAI YOKOREI CO., LTD.
Status: New
Start date: 16 Jan 2026
Due date:
Assignee:
Priority: Normal
Project progress work #4441: [Requirement Definition] Project progress work #4441: [Requirement Definition]

Project: THAI YOKOREI CO., LTD.
Status: In Progress
Start date: 16 Jan 2026
Due date:
Assignee:
Priority: Normal
Parent project #4385: [PJ260002] Camera system mo... Parent project #4385: [PJ260002] Camera system modification for Thailand configuration BCR

Project: THAI YOKOREI CO., LTD.
Status: In Progress
Start date: 16 Jan 2026
Due date:
Assignee: Nattapol Poeam
Priority: Normal
Parent project #4384: [PJ260001] BCR system for T... Parent project #4384: [PJ260001] BCR system for Thai Yokorei

Project: THAI YOKOREI CO., LTD.
Status: In Progress
Start date: 16 Jan 2026
Due date:
Assignee: Nattapol Poeam
Priority: Normal

17

4

18

19

20

21

22

23

24

5

25

26

27

28

29

30

31

issue beginning this day issue ending this day issue beginning and ending this day