Hours: 1442.00

Date User Activity Issue Comment Hours
06 Feb 2024 Suthiwat Banrueangthong Design Project progress work #400: Program developer and Dashboard design Design signals that require Plant B along with design 8.00 Actions
05 Feb 2024 Nattapol Poeam Installation Project progress work #126: [Installation&On-site support] Production IoT system for TNF Power on TB-Box Plant A and Data monitor from Machine Spiral 8.00 Actions
05 Feb 2024 Suthiwat Banrueangthong Installation Project progress work #399: [Installation&On-site support] Production IoT system for TNF Test PLC signal reception 8.00 Actions
04 Feb 2024 Suthiwat Banrueangthong Installation Project progress work #399: [Installation&On-site support] Production IoT system for TNF Finished wiring from the ceiling down to all plantB machines and installing plc connection equipment. 8.00 Actions
03 Feb 2024 Nattapol Poeam Installation Project progress work #126: [Installation&On-site support] Production IoT system for TNF Monitoring and communication test on Plant A 8.00 Actions
03 Feb 2024 Suthiwat Banrueangthong Installation Project progress work #399: [Installation&On-site support] Production IoT system for TNF Run the cable from the ceiling down to the plantB machine. 8.00 Actions
02 Feb 2024 Suthiwat Banrueangthong Design Project progress work #400: Program developer and Dashboard design Set all required bits in plant A 8.00 Actions
01 Feb 2024 Nattapol Poeam Make document Sales support #86: IoT Equipment for Water treatment project Summarize equipment and check spec device 4.00 Actions
01 Feb 2024 Suthiwat Banrueangthong Design Project progress work #400: Program developer and Dashboard design design machine Polystar 8.00 Actions
01 Feb 2024 Suthiwat Banrueangthong Installation Project progress work #422: Install PLC programs Install PLC programs kv studio,vt studio,GX-Work2,gt designer 3 8.00 Actions
31 Jan 2024 Suthiwat Banrueangthong Design Project progress work #400: Program developer and Dashboard design design dashboard Spiral machine 8.00 Actions
30 Jan 2024 Suthiwat Banrueangthong Design Project progress work #400: Program developer and Dashboard design Set the required bit of the Spiral machine. 8.00 Actions
30 Jan 2024 Nattapol Poeam Installation Project progress work #126: [Installation&On-site support] Production IoT system for TNF Installation TB-Box in Plant A 8.00 Actions
29 Jan 2024 Suthiwat Banrueangthong Design Project progress work #400: Program developer and Dashboard design Set the required bit of the Spiral machine. 8.00 Actions
28 Jan 2024 Suthiwat Banrueangthong Installation Project progress work #399: [Installation&On-site support] Production IoT system for TNF Route the I/O cables on the ceiling to the machine location. 8.00 Actions
26 Jan 2024 Suthiwat Banrueangthong Design Project progress work #400: Program developer and Dashboard design summax machine design 8.00 Actions
25 Jan 2024 Suthiwat Banrueangthong Design Project progress work #400: Program developer and Dashboard design Set the bit that must be used by the summax machine. 4.00 Actions
24 Jan 2024 Suthiwat Banrueangthong Design Project progress work #400: Program developer and Dashboard design Hi-cook machine design completed 4.00 Actions
23 Jan 2024 Suthiwat Banrueangthong Design Project progress work #400: Program developer and Dashboard design Hicook machine design 8.00 Actions
23 Jan 2024 Nattapol Poeam Make document Project progress work #403: Summarize equipment of Water treatment project Summarize equipment 8.00 Actions
22 Jan 2024 Suthiwat Banrueangthong Design Project progress work #400: Program developer and Dashboard design H-icook machine design 8.00 Actions
20 Jan 2024 Suthiwat Banrueangthong Installation Project progress work #399: [Installation&On-site support] Production IoT system for TNF Wiring the ceiling from the plantB cabinet 8.00 Actions
19 Jan 2024 Suthiwat Banrueangthong Design Project progress work #400: Program developer and Dashboard design Set the required bit for each machine. 8.00 Actions
18 Jan 2024 Suthiwat Banrueangthong Design Project progress work #400: Program developer and Dashboard design Set the required bit for each machine. 8.00 Actions
18 Jan 2024 Nattapol Poeam Installation Sales support #86: IoT Equipment for Water treatment project Site survey 4.00 Actions