Hours: 23.00

Date User Activity Issue Comment Hours
14 Nov 2023 Nattapol Poeam Make document Project progress work #201: Summary of all equipment for use in the Machine operation monitoring systems project. Update list equipment of TNF project 3.00 Actions
13 Nov 2023 Nattapol Poeam Make document Project progress work #201: Summary of all equipment for use in the Machine operation monitoring systems project. Follow up quote form supplier 2.00 Actions
10 Nov 2023 Nattapol Poeam Make document Project progress work #201: Summary of all equipment for use in the Machine operation monitoring systems project. Summarize equipment before order 5.00 Actions
09 Nov 2023 Nattapol Poeam Make document Project progress work #201: Summary of all equipment for use in the Machine operation monitoring systems project. Summarize equipment before order 5.00 Actions
07 Nov 2023 Nattapol Poeam Meeting Project progress work #201: Summary of all equipment for use in the Machine operation monitoring systems project. Online meeting about Demo-kit YAMADA SOMBOON CO.,LTD 3.00 Actions
07 Nov 2023 Nattapol Poeam Design Project progress work #201: Summary of all equipment for use in the Machine operation monitoring systems project. Revise and summarize all equipment of the Machine operation monitoring system project. 5.00 Actions