44

26

27

28

29

30

31

1

45

2

3

Project progress work #2865: [Installation&On-site suppo... Project progress work #2865: [Installation&On-site support] Go live

Project: THAI INABA FOODS COMPANY LIMITED
Status: In Progress
Start date: 03 Nov 2025
Due date:
Assignee: Taweesak Prumvised
Priority: Normal

4

5

6

Project progress work #2867: [Coding] HT Pegasus add re-... Project progress work #2867: [Coding] HT Pegasus add re-check function

Project: THAI INABA FOODS COMPANY LIMITED
Status: New
Start date: 06 Nov 2025
Due date: 08 Nov 2025
Assignee: Taweesak Prumvised
Priority: Normal

7

8

Project progress work #2867: [Coding] HT Pegasus add re-... Project progress work #2867: [Coding] HT Pegasus add re-check function

Project: THAI INABA FOODS COMPANY LIMITED
Status: New
Start date: 06 Nov 2025
Due date: 08 Nov 2025
Assignee: Taweesak Prumvised
Priority: Normal
46

9

10

11

12

13

14

15

47

16

17

18

19

20

21

Project progress work #2878: [installation&On-site suppo... Project progress work #2878: [installation&On-site support] Support Onsite

Project: THAI INABA FOODS COMPANY LIMITED
Status: In Progress
Start date: 21 Nov 2025
Due date:
Assignee: Nattaporn Chaiya
Priority: Normal

22

48

23

24

25

26

27

28

29

49

30

1

2

3

4

5

6