07 Nov 2025

16:45 8.00 hours (Project progress work #2878 (In Progress): [installation&On-site support] Support Onsite)
Support Onsite Nattaporn Chaiya
16:45 8.00 hours (Project progress work #2878 (In Progress): [installation&On-site support] Support Onsite)
Support Onsite Nattaporn Chaiya
16:45 8.00 hours (Project progress work #2878 (In Progress): [installation&On-site support] Support Onsite)
Onsite Nattaporn Chaiya
16:44 8.00 hours (Project progress work #2878 (In Progress): [installation&On-site support] Support Onsite)
Onsite Nattaporn Chaiya
16:44 8.00 hours (Project progress work #2878 (In Progress): [installation&On-site support] Support Onsite)
Onsite Nattaporn Chaiya
16:44 8.00 hours (Project progress work #2878 (In Progress): [installation&On-site support] Support Onsite)
Onsite Nattaporn Chaiya
16:43 8.00 hours (Project progress work #2878 (In Progress): [installation&On-site support] Support Onsite)
Onsite Nattaporn Chaiya
16:28 32.00 hours (Project progress work #1479 (Closed): [Coding] Stock Re-Check)
17-20 Sep 2025 Stock Re-check Nattaporn Chaiya
16:26 8.00 hours (Project progress work #1476 (Closed): [Coding] Outbound SEMI)
Outbound SEMI Nattaporn Chaiya
16:26 8.00 hours (Project progress work #1476 (Closed): [Coding] Outbound SEMI)
Outbound SEMI Nattaporn Chaiya
16:25 8.00 hours (Project progress work #1476 (Closed): [Coding] Outbound SEMI)
Outbound SEMI Nattaporn Chaiya
16:25 8.00 hours (Project progress work #1476 (Closed): [Coding] Outbound SEMI)
Outbound SEMI Nattaporn Chaiya
16:25 8.00 hours (Project progress work #1476 (Closed): [Coding] Outbound SEMI)
Outbound SEMI Nattaporn Chaiya
16:25 8.00 hours (Project progress work #1476 (Closed): [Coding] Outbound SEMI)
Outbound SEMI Nattaporn Chaiya
16:24 8.00 hours (Project progress work #1476 (Closed): [Coding] Outbound SEMI)
Outbound SEMI Nattaporn Chaiya
16:24 8.00 hours (Project progress work #1476 (Closed): [Coding] Outbound SEMI)
Outbound SEMI Nattaporn Chaiya
16:24 8.00 hours (Project progress work #1476 (Closed): [Coding] Outbound SEMI)
Outbound SEMI Nattaporn Chaiya
16:24 8.00 hours (Project progress work #1476 (Closed): [Coding] Outbound SEMI)
Outbound SEMI Nattaporn Chaiya
16:21 8.00 hours (Project progress work #1475 (Closed): [Coding] Inbound FG)
Inbound FG Nattaporn Chaiya
16:21 8.00 hours (Project progress work #1475 (Closed): [Coding] Inbound FG)
Inbound FG Nattaporn Chaiya
16:21 8.00 hours (Project progress work #1475 (Closed): [Coding] Inbound FG)
Inbound FG Nattaporn Chaiya
16:20 8.00 hours (Project progress work #1475 (Closed): [Coding] Inbound FG)
Inbound FG Nattaporn Chaiya
16:20 8.00 hours (Project progress work #1475 (Closed): [Coding] Inbound FG)
Inbound FG Nattaporn Chaiya
16:17 8.00 hours (Project progress work #1474 (Closed): [Coding] Inbound SEMI)
Inbound SEMI Nattaporn Chaiya
16:17 8.00 hours (Project progress work #1474 (Closed): [Coding] Inbound SEMI)
Inbound SEMI Nattaporn Chaiya
16:17 8.00 hours (Project progress work #1474 (Closed): [Coding] Inbound SEMI)
Inbound SEMI Nattaporn Chaiya
16:16 8.00 hours (Project progress work #1474 (Closed): [Coding] Inbound SEMI)
Inbound SEMI Nattaporn Chaiya
16:16 8.00 hours (Project progress work #1474 (Closed): [Coding] Inbound SEMI)
Inbound SEMI Nattaporn Chaiya
16:12 8.00 hours (Project progress work #1448 (Closed): [Coding] Schedule)
Schedule Nattaporn Chaiya
16:12 8.00 hours (Project progress work #1448 (Closed): [Coding] Schedule)
Schedule Nattaporn Chaiya
16:12 8.00 hours (Project progress work #1448 (Closed): [Coding] Schedule)
Schedule Nattaporn Chaiya
16:11 8.00 hours (Project progress work #1448 (Closed): [Coding] Schedule)
Schedule Nattaporn Chaiya
16:11 8.00 hours (Project progress work #1448 (Closed): [Coding] Schedule)
Schedule Nattaporn Chaiya
16:11 8.00 hours (Project progress work #1448 (Closed): [Coding] Schedule)
Schedule Nattaporn Chaiya
16:10 8.00 hours (Project progress work #1448 (Closed): [Coding] Schedule)
Schedule Nattaporn Chaiya
16:10 8.00 hours (Project progress work #1448 (Closed): [Coding] Schedule)
Schedule Nattaporn Chaiya
16:10 8.00 hours (Project progress work #1448 (Closed): [Coding] Schedule)
Schedule Nattaporn Chaiya
16:10 8.00 hours (Project progress work #1448 (Closed): [Coding] Schedule)
Schedule Nattaporn Chaiya
16:09 8.00 hours (Project progress work #1448 (Closed): [Coding] Schedule)
Schedule Nattaporn Chaiya
16:09 8.00 hours (Project progress work #1448 (Closed): [Coding] Schedule)
Schedule Nattaporn Chaiya
16:09 8.00 hours (Project progress work #1448 (Closed): [Coding] Schedule)
Schedule Nattaporn Chaiya
16:09 8.00 hours (Project progress work #1448 (Closed): [Coding] Schedule)
Schedule Nattaporn Chaiya
16:08 8.00 hours (Project progress work #1448 (Closed): [Coding] Schedule)
Schedule Nattaporn Chaiya
16:08 8.00 hours (Project progress work #1448 (Closed): [Coding] Schedule)
Schedule Nattaporn Chaiya
16:08 8.00 hours (Project progress work #1448 (Closed): [Coding] Schedule)
Schedule Nattaporn Chaiya
16:07 8.00 hours (Project progress work #1448 (Closed): [Coding] Schedule)
Schedule Nattaporn Chaiya
16:07 8.00 hours (Project progress work #1448 (Closed): [Coding] Schedule)
Schedule Nattaporn Chaiya
16:02 8.00 hours (Project progress work #1446 (Closed): [Coding] Stock Management)
Inaba Stock 3/3 Siriwilai Chaiwattanaphon
16:02 8.00 hours (Project progress work #1446 (Closed): [Coding] Stock Management)
Inaba Stock 2/3 Siriwilai Chaiwattanaphon
16:02 8.00 hours (Project progress work #1446 (Closed): [Coding] Stock Management)
Inaba Stock 1/3 Siriwilai Chaiwattanaphon
06:33 8.00 hours (Project progress work #2863 (In Progress): [Coding] HT Pegasus fix issue after on site)
Fixed issues. Taweesak Prumvised
 