18 Oct 2025

16:24 2.00 hours (Project progress work #1014 (Closed): [Coding] Warehouse management system handyterminal Java)
Edit tag label. Taweesak Prumvised

17 Oct 2025

17:12 8.00 hours (Project progress work #1014 (Closed): [Coding] Warehouse management system handyterminal Java)
On site UAT test. Taweesak Prumvised
17:11 8.00 hours (Project progress work #1014 (Closed): [Coding] Warehouse management system handyterminal Java)
Fixed punch list after on site UAT Test. Taweesak Prumvised
16:34 2.00 hours (Project progress work #1015 (New): [Cording] Warehouse management system PHP)
Fix issues and Update User Master Nattaporn Chaiya
16:34 2.00 hours (Project progress work #1015 (New): [Cording] Warehouse management system PHP)
Internal Meeting Nattaporn Chaiya

15 Oct 2025

17:58 8.00 hours (Project progress work #1014 (Closed): [Coding] Warehouse management system handyterminal Java)
Internal test. Taweesak Prumvised
15:22 8.00 hours (Project progress work #1477 (Closed): [Coding] API Difuku)
Update API Daifuku Nattaporn Chaiya

14 Oct 2025

17:06 4.00 hours (Project progress work #1014 (Closed): [Coding] Warehouse management system handyterminal Java)
Edit condition of AS/RS. Taweesak Prumvised

10 Oct 2025

16:17 8.00 hours (Project progress work #1449 (In Progress): [Coding] Software test and fixed )
Fix issues After UAT Nattaporn Chaiya
09:36 8.00 hours (Project progress work #1449 (In Progress): [Coding] Software test and fixed )
UAT Test function Group lot, SEMI Nattaporn Chaiya
12:55 4.00 hours (Project progress work #1014 (Closed): [Coding] Warehouse management system handyterminal Java)
HT pegasus test. Taweesak Prumvised
07:07 8.00 hours (Project progress work #1014 (Closed): [Coding] Warehouse management system handyterminal Java)
On site review all functions. Taweesak Prumvised
 