Parent project #1284: [PJ250039] Infrastructure IoT system for Thai Asahi Denso
Project progress work #1408: [Coding] Windows app & Back-end
Project progress work #1288: [Installation&On-site support] Software installation
Project progress work #2933: [Installation&On-site support] SIT Utility system
Project progress work #2934: [Installation&On-site support] UAT
Project progress work #2932: [Installation&On-site support] SIT Production system
Project progress work #4423: [Installation&On-site support]
Project progress work #1287: [Coding] Web application
Project progress work #1285: [Requirement definition]
Parent project #2722: [PJ250068] IoT system for THAI ASAHI DENSO CO., LTD additional cost
Project progress work #2726: [Installation&On-site support]
Project progress work #2723: [Requirement definition]

Status

In Progress
In Progress
In Progress
In Progress
In Progress
In Progress
In Progress
In Progress
In Progress
In Progress
In Progress
In Progress
In Progress
In Progress

Priority

Normal
Normal
Normal
Normal
Normal
Normal
Normal
Normal
Normal
Normal
Normal
Normal
Normal
Normal

Total estimated time

2944.00
392.00
760.00
40.00
72.00
272.00
432.00
176.00
80.00
16.00
144.00
120.00
16.00
8.00

Total spent time

0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00

Updated

29 May 2026 15:20
24 Feb 2026 16:09
26 May 2026 11:12
24 Feb 2026 16:04
26 May 2026 11:12
26 May 2026 11:12
08 May 2026 11:37
08 Apr 2026 10:47
05 Jun 2026 15:22
26 May 2026 11:16
20 Jun 2026 15:38
20 Jun 2026 15:38
12 Jun 2026 16:33
26 May 2026 11:38
 
 
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
Tomas Tech All Project Management
 
 
THAI ASAHI DENSO CO., LTD.
 
 
 
 
In Progress
Parent project #1284: [PJ250039] Infrastructure IoT system for Thai Asahi Denso

Project: THAI ASAHI DENSO CO., LTD.
Status: In Progress
Start date: 14 Aug 2025
Due date: 29 May 2026
Assignee: Nattapol Poeam
Priority: Normal
 
 
 
 
In Progress 100%
Project progress work #1408: [Coding] Windows app & Back-end

Project: THAI ASAHI DENSO CO., LTD.
Status: In Progress
Start date: 07 Sep 2025
Due date: 13 Feb 2026
Assignee: Pattanasak Chaonchom
Priority: Normal
 
 
 
 
In Progress 99%
Project progress work #1288: [Installation&On-site support] Software installation

Project: THAI ASAHI DENSO CO., LTD.
Status: In Progress
Start date: 17 Nov 2025
Due date: 06 Mar 2026
Assignee:
Priority: Normal
In Progress 100%
In Progress 100%
In Progress 99%
 
 
 
 
In Progress 100%
Project progress work #4423: [Installation&On-site support]

Project: THAI ASAHI DENSO CO., LTD.
Status: In Progress
Start date: 04 Dec 2025
Due date: 11 Mar 2026
Assignee:
Priority: Normal
 
 
 
 
In Progress 100%
Project progress work #1287: [Coding] Web application

Project: THAI ASAHI DENSO CO., LTD.
Status: In Progress
Start date: 09 Dec 2025
Due date: 03 Apr 2026
Assignee: Worawit Khantamool
Priority: Normal
 
 
 
 
In Progress 100%
Problem-Bug #4400: [Issue]

Project: THAI ASAHI DENSO CO., LTD.
Status: In Progress
Start date: 15 Dec 2025
Due date: 23 May 2026
Assignee: Worawit Khantamool
Priority: Normal
 
 
 
 
 
In Progress 100%
Project progress work #1285: [Requirement definition]

Project: THAI ASAHI DENSO CO., LTD.
Status: In Progress
Start date: 15 May 2026
Due date: 19 May 2026
Assignee:
Priority: Normal
 
 
 
 
In Progress
Parent project #2722: [PJ250068] IoT system for THAI ASAHI DENSO CO., LTD additional cost

Project: THAI ASAHI DENSO CO., LTD.
Status: In Progress
Start date: 29 Oct 2025
Due date: 12 Jun 2026
Assignee: Nattapol Poeam
Priority: Normal
 
 
 
 
In Progress 99%
Project progress work #2725: [Coding]

Project: THAI ASAHI DENSO CO., LTD.
Status: In Progress
Start date: 03 Dec 2025
Due date: 12 Jun 2026
Assignee: Nattapol Poeam
Priority: Normal
 
 
 
 
 
In Progress 100%
Project progress work #2726: [Installation&On-site support]

Project: THAI ASAHI DENSO CO., LTD.
Status: In Progress
Start date: 11 May 2026
Due date: 26 May 2026
Assignee: Nattapol Poeam
Priority: Normal
 
 
 
 
 
In Progress 100%
Project progress work #2723: [Requirement definition]

Project: THAI ASAHI DENSO CO., LTD.
Status: In Progress
Start date: 15 May 2026
Due date: 15 May 2026
Assignee: Nattapol Poeam