Parent project #1047: [PJ250025] Pokayoke inspection system for SIAM NITERRA Co., Ltd.
Project progress work #1051: [Installation&On-site support]

Status

In Progress
New
New

Priority

Normal
Normal
Normal

Total estimated time

16.00
16.00

Total spent time

0.00
0.00
0.00

Updated

25 Mar 2026 15:15
06 Aug 2025 11:37
12 Mar 2026 11:47
 
 
41
42
43
44
45
46
47
48
49
50
51
52
1
2
3
4
5
6
7
8
9
10
11
12
13
Tomas Tech All Project Management
 
 
SIAM NITERRA CO., LTD.
 
 
 
 
In Progress
Parent project #1047: [PJ250025] Pokayoke inspection system for SIAM NITERRA Co., Ltd.

Project: SIAM NITERRA CO., LTD.
Status: In Progress
Start date: 01 Jun 2025
Due date: 26 Jan 2026
Assignee: Nattapol Poeam
Priority: Normal
New 0%
 
 
 
 
 
New 100%
Project progress work #1051: [Installation&On-site support]

Project: SIAM NITERRA CO., LTD.
Status: New
Start date: 24 Jan 2026
Due date: 26 Jan 2026
Assignee: Nattapol Poeam
Priority: Normal