24 Jul 2024 Konlawat Saechee Meeting Project progress work #645: [ Installation&On-site support ] Power meter monitoring system for OTICS Buy Transformer at Ban Mo Plaza 4.00 Actions
24 Jul 2024 Teeradon Yuensakul Installation Project progress work #645: [ Installation&On-site support ] Power meter monitoring system for OTICS Power Meter Communication Setting 8.00 Actions
24 Jul 2024 Phatthadon Inthachot Installation Project progress work #645: [ Installation&On-site support ] Power meter monitoring system for OTICS Wiring cabinet IoT OTICS 8.00 Actions
23 Jul 2024 Phatthadon Inthachot Installation Project progress work #645: [ Installation&On-site support ] Power meter monitoring system for OTICS Wiring cabinet IoT OTICS 8.00 Actions
22 Jul 2024 Phatthadon Inthachot Installation Project progress work #645: [ Installation&On-site support ] Power meter monitoring system for OTICS Support installation 8.00 Actions
19 Jul 2024 Teeradon Yuensakul Development Project progress work #502: [Coding] Infrastructure IoT system for OTICS(Thailand) PLC Keyence 8.00 Actions
18 Jul 2024 Teeradon Yuensakul Taking Day off Project progress work #502: [Coding] Infrastructure IoT system for OTICS(Thailand) PLC Keyence 8.00 Actions
18 Jul 2024 Phatthadon Inthachot Design Project progress work #636: Electrical drawing design Wiring Diagram and PR part list 8.00 Actions
17 Jul 2024 Teeradon Yuensakul Taking Day off Project progress work #502: [Coding] Infrastructure IoT system for OTICS(Thailand) PLC Keyence 8.00 Actions
16 Jul 2024 Teeradon Yuensakul Development Project progress work #502: [Coding] Infrastructure IoT system for OTICS(Thailand) PLC Keyence 8.00 Actions
16 Jul 2024 Nattapol Poeam Meeting Project progress work #596: [Requirement and support] Infrastructure IoT system for OTICS(Thailand) Meeting about mark position installation cabrinet control and test program 8.00 Actions
15 Jul 2024 Teeradon Yuensakul Development Project progress work #502: [Coding] Infrastructure IoT system for OTICS(Thailand) PLC Keyence 8.00 Actions
13 Jul 2024 Teeradon Yuensakul Development Project progress work #502: [Coding] Infrastructure IoT system for OTICS(Thailand) PLC Keyence 8.00 Actions
13 Jul 2024 Phatthadon Inthachot Installation Project progress work #645: [ Installation&On-site support ] Power meter monitoring system for OTICS Support installation 8.00 Actions
12 Jul 2024 Teeradon Yuensakul Development Project progress work #502: [Coding] Infrastructure IoT system for OTICS(Thailand) PLC Keyence 8.00 Actions
11 Jul 2024 Teeradon Yuensakul Development Project progress work #502: [Coding] Infrastructure IoT system for OTICS(Thailand) PLC Keyence 8.00 Actions
10 Jul 2024 Phatthadon Inthachot Make document Project progress work #636: Electrical drawing design PR Electrical part list 8.00 Actions
10 Jul 2024 Teeradon Yuensakul Development Project progress work #502: [Coding] Infrastructure IoT system for OTICS(Thailand) PLC Keyence 8.00 Actions
09 Jul 2024 Teeradon Yuensakul Development Project progress work #502: [Coding] Infrastructure IoT system for OTICS(Thailand) PLC Keyence 8.00 Actions
08 Jul 2024 Teeradon Yuensakul Development Project progress work #502: [Coding] Infrastructure IoT system for OTICS(Thailand) PLC Keyence programming PLC 8.00 Actions
05 Jul 2024 Phatthadon Inthachot Make document Project progress work #636: Electrical drawing design PR Electrical part list 8.00 Actions
05 Jul 2024 Teeradon Yuensakul Development Project progress work #502: [Coding] Infrastructure IoT system for OTICS(Thailand) PLC Keyence programming PLC 8.00 Actions
04 Jul 2024 Teeradon Yuensakul Development Project progress work #502: [Coding] Infrastructure IoT system for OTICS(Thailand) PLC Keyence programming PLC 8.00 Actions
03 Jul 2024 Teeradon Yuensakul Development Project progress work #502: [Coding] Infrastructure IoT system for OTICS(Thailand) PLC Keyence programming PLC 8.00 Actions
02 Jul 2024 Phatthadon Inthachot Make document Project progress work #636: Electrical drawing design PR Electrical part list 8.00 Actions