Hours: 1440.00

Date User Activity Issue Comment Hours
22 Aug 2024 Teeradon Yuensakul Development Project progress work #675: Program Testing 8.00 Actions
22 Aug 2024 Priroj Neamjarn Development Project progress work #679: Power meter monitoring Fix bug receive log data 8.00 Actions
22 Aug 2024 Priroj Neamjarn Development Project progress work #679: Power meter monitoring Fix bug receive log data 8.00 Actions
21 Aug 2024 Teeradon Yuensakul Development Project progress work #675: Program Testing 8.00 Actions
21 Aug 2024 Teeradon Yuensakul Development Project progress work #675: Program Testing 8.00 Actions
21 Aug 2024 Teeradon Yuensakul Development Project progress work #675: Program Testing 8.00 Actions
21 Aug 2024 Worawit Khantamool Development Project progress work #503: [Coding] Infrastructure IoT system for OTICS(Thailand) PHP Pull data from DB into Dashboard - Yearly monthly bar chart display (100%), - Monthly daily bar chart display (100%), - Daily hourly bar chart display (100%) 8.00 Actions
20 Aug 2024 Nattapol Poeam Installation Project progress work #645: [ Installation&On-site support ] Power meter monitoring system for OTICS Install and debug program 8.00 Actions
20 Aug 2024 Teeradon Yuensakul Development Project progress work #675: Program Testing 8.00 Actions
20 Aug 2024 Worawit Khantamool Development Project progress work #503: [Coding] Infrastructure IoT system for OTICS(Thailand) PHP Pull data from DB into Dashboard - Weekly cost bar chart display (100%), - Daily cost bar chart display (100%) 8.00 Actions
20 Aug 2024 Priroj Neamjarn Installation Project progress work #679: Power meter monitoring Installation 4.00 Actions
20 Aug 2024 Priroj Neamjarn Installation Project progress work #679: Power meter monitoring Installation 4.00 Actions
19 Aug 2024 Nattapol Poeam Installation Project progress work #645: [ Installation&On-site support ] Power meter monitoring system for OTICS Installation 8.00 Actions
19 Aug 2024 Teeradon Yuensakul Development Project progress work #675: Program Testing 8.00 Actions
19 Aug 2024 Priroj Neamjarn Installation Project progress work #679: Power meter monitoring make manual and installation 8.00 Actions
19 Aug 2024 Priroj Neamjarn Development Project progress work #679: Power meter monitoring make manual and installation 8.00 Actions
19 Aug 2024 Priroj Neamjarn Installation Project progress work #679: Power meter monitoring make manual and installation 8.00 Actions
16 Aug 2024 Nattapol Poeam Development Project progress work #688: [ Task ] Coding C# Transfer data PLC to DB Program developer 8.00 Actions
16 Aug 2024 Teeradon Yuensakul Development Project progress work #675: Program Testing 8.00 Actions
16 Aug 2024 Priroj Neamjarn Development Project progress work #679: Power meter monitoring Unit Test ,Fix bug 8.00 Actions
16 Aug 2024 Priroj Neamjarn Development Project progress work #679: Power meter monitoring Unit Test ,Fix bug 8.00 Actions
15 Aug 2024 Nattapol Poeam Development Project progress work #688: [ Task ] Coding C# Transfer data PLC to DB Program developer 8.00 Actions
15 Aug 2024 Teeradon Yuensakul Development Project progress work #675: Program Testing 8.00 Actions
15 Aug 2024 Worawit Khantamool Development Project progress work #503: [Coding] Infrastructure IoT system for OTICS(Thailand) PHP Pull data from DB into Dashboard - Monthly cost bar chart display (100%) 8.00 Actions
15 Aug 2024 Priroj Neamjarn Development Project progress work #679: Power meter monitoring Coding export dashboard 8.00 Actions
(51-75/185) Per page: 25, 50, 100