# Tracker Status Priority Subject Assignee Total estimated time Total spent time Updated
6915 Project progress work New Normal [Installation&On-site support] 8.00 0.00 11 Mar 2026 16:47 Actions
6914 Project progress work New Normal [Coding] 0.00 11 Mar 2026 16:45 Actions
6913 Project progress work New Normal [Internal Design] 0.00 11 Mar 2026 16:45 Actions
6912 Project progress work New Normal [Requirement definition] 0.00 11 Mar 2026 16:44 Actions
3247 Parent project In Progress Normal [PJ250100] ConMas i-Reporter 05 users On-premises #2 8.00 0.00 11 Mar 2026 16:47 Actions
2768 Project progress work New Normal [Installation&On-site support] Anek Sanohkham 8.00 0.00 26 Feb 2026 13:27 Actions
2767 Project progress work New Normal [Coding] Anek Sanohkham 0.00 29 Oct 2025 15:33 Actions
2766 Project progress work New Normal [Internal Design] Anek Sanohkham 0.00 29 Oct 2025 15:32 Actions
2765 Project progress work New Normal [Requirement definition] Anek Sanohkham 0.00 29 Oct 2025 15:32 Actions
2764 Parent project In Progress Normal [PJ250075] ConMas i-Reporter Trial IP Settings 50% Anek Sanohkham 8.00 0.00 26 Feb 2026 13:27 Actions