open[PJ260091] Robot Handling Machine
Updated by Waraporn Promsopa 4 days ago
1 Standard equipment cost
1-1 Nachi : MZ07LF-01-000-CFDS-0000F 1 set
1-2 IAI : ICSB3-BE1HB3M-WA-80AQ-60AQ-15AQB-T4-5L-CT-CT 1 set
1-3 Modify PLC "Press Machine" to Master Control " 1 set
1-4 Modify PLC "Inspection Machine" to Master Control " 1 set
2 Electical cost
2-1 Master Control Box 1 set
2-2 Field Wiring : Tray Supply (York) Unit 1 set
2-3 Field Wiring : Robot (6-Axis) Pick and Place Unit 1 set
2-4 Field Wiring : Tray Supply (Sheet) Unit 1 set
2-5 Field Wiring : Finish Good 1 set
2-6 Field Wiring : Safety Fence Unit 1 set
2-7 Field Wiring : Modify PLC "Press and Inspection Machine" for New Master Control 1 set
3 Mechanical cost
3-1 Tray Supply (York) Unit 1 set
3-2 Tray Supply (FG) Unit 1 set
3-3 Robot (6-Axis) Pick and Place Unit 1 set
3-4 Robot (Cartesian) Pick and Place Unit 1 set
3-5 Tray Supply (Sheet) Unit 1 set
3-6 Safety Fence Unit 1 set
3-7 Press Machine (Modify) Unit 1 set
3-8 Wire Way Unit 1 set
3-9 Solenoid Valve and Air Unit 1 set
4 Engineering cost
4-1 Design < Hardware and Software > 1 Job
Assembly / Wirring ,Test Run / BuyOff
Modify Existing Press and Inspection Machine (Include Transportation)
5 Installation and Commissioning
5-1 Installation and Wirring 1 Job
IO check and Sofware Debug
Test Run and Machine Commistioning
Include :
set
set
1 Job
55,600.00 55,600.00
1 set 16,700.00
509,400.00 509,400.00
1 Job 225,000.00 225,000.00
Transportation and Tool
Safety check and Quality check
Stand By Production (3 Days ,1 Shift)
Note )
1. Customer provide Primary Power and Air (Drop Point)
2. Customer provide the sample for enough test
3. Customer provide Tray for York ,Sheet and FG
4. Customer provide Inspection machine 2 set ( with samilar ) for modify at Tomas around 1 month
5. Customer provide Press Machine for modify at Tomas around 1 month
6. Customer provide Forklift for Loading and Unloading mcahine
Remark :
50% DP upon PO Credit 7days
20% after Design Finished and Before arranging parts Credit 30days
10% after When installing the product Credit 30days
10% after Finished installation Credit 30days
10% after Finished handover Credit 30days
Delivery : 5 - 6 Months (After PO) or by Discussion