Project

General

Profile

Spent time

Filters

Apply Clear

Hours: 345.00

Date User Activity Issue Comment Hours
17 Sep 2024 Kittisak Isarapongporn Development Project progress work #673: [Settings] Asprova implementation Asprova setting and test 3.00 Actions
17 Sep 2024 Kittisak Isarapongporn Meeting Project progress work #673: [Settings] Asprova implementation 5.00 Actions
07 Sep 2024 Kittisak Isarapongporn Development Project progress work #673: [Settings] Asprova implementation 8.00 Actions
06 Sep 2024 Kittisak Isarapongporn Development Project progress work #673: [Settings] Asprova implementation 7.00 Actions
05 Sep 2024 Kittisak Isarapongporn Development Project progress work #673: [Settings] Asprova implementation 8.00 Actions
04 Sep 2024 Kittisak Isarapongporn Development Project progress work #673: [Settings] Asprova implementation 8.00 Actions
30 Aug 2024 Kittisak Isarapongporn Development Project progress work #673: [Settings] Asprova implementation Check more details regarding to new requirements from user 4.00 Actions
29 Aug 2024 Kittisak Isarapongporn Meeting Project progress work #673: [Settings] Asprova implementation 4.00 Actions
29 Aug 2024 Kittisak Isarapongporn Development Project progress work #673: [Settings] Asprova implementation Check master data 4.00 Actions
28 Aug 2024 Kittisak Isarapongporn Development Project progress work #673: [Settings] Asprova implementation 8.00 Actions
24 Aug 2024 Kittisak Isarapongporn Development Project progress work #673: [Settings] Asprova implementation Try to generate the production schedule and check the item master 8.00 Actions
19 Aug 2024 Kittisak Isarapongporn Development Project progress work #673: [Settings] Asprova implementation Check master and enter order sales data for planning 4.00 Actions
06 Aug 2024 Kittisak Isarapongporn Installation Project progress work #673: [Settings] Asprova implementation Install the asprova but found the problem about expired license. 3.00 Actions
25 Jul 2024 Kittisak Isarapongporn Meeting Project progress work #673: [Settings] Asprova implementation Meeting, check materials and requirements 2.00 Actions
05 Jul 2024 Soraya Norasing Meeting Project progress work #504: [Setting] Production planning system APS 500,000 work Prepare a form to enter order information for customers. and meeting with customer at factory 8.00 Actions
21 Jun 2024 Soraya Norasing Meeting Project progress work #504: [Setting] Production planning system APS 500,000 work Meeting with customer at NTPT. The information sent by the customer has been confirmed.: Shift, machine/ The information sent by the customer has been confirmed.: BOM, Item (Will send it within 3 July.) 6.00 Actions
13 Jun 2024 Soraya Norasing Development Project progress work #464: Learn to use the Asprova program. Study the program's user manual. 5.00 Actions
07 Jun 2024 Soraya Norasing Meeting Project progress work #504: [Setting] Production planning system APS 500,000 work Study the Aspova program manual. meeting with customer at factory 8.00 Actions
06 Jun 2024 Soraya Norasing Development Project progress work #504: [Setting] Production planning system APS 500,000 work Study the Aspova program manual. (Bacis) Learn about tables and data collection. 8.00 Actions
31 May 2024 Soraya Norasing Development Project progress work #504: [Setting] Production planning system APS 500,000 work Study the use of the Asprova program.(video clip) 4.00 Actions
30 May 2024 Soraya Norasing Make document Project progress work #504: [Setting] Production planning system APS 500,000 work Design document forms and Study the use of the Esprova program. 8.00 Actions
29 May 2024 Soraya Norasing Make document Project progress work #504: [Setting] Production planning system APS 500,000 work Modify Specifications Documentation R3 and Design document form 8.00 Actions
28 May 2024 Soraya Norasing Make document Project progress work #504: [Setting] Production planning system APS 500,000 work View documents, contact, request an explanation with the customer. and design forms 8.00 Actions
15 May 2024 Soraya Norasing Make document Project progress work #504: [Setting] Production planning system APS 500,000 work Modify Asprova system Specifications Documentation 5.00 Actions
14 May 2024 Soraya Norasing Make document Project progress work #504: [Setting] Production planning system APS 500,000 work Create the Asprova specification document. 6.00 Actions
(26-50/58) Per page: 25, 50, 100

Also available in: Atom CSV