From 27 Aug 2024 to 05 Sep 2024
02 Sep 2024
- 00:56 4.00 hours (Project progress work #673 (In Progress): [Settings] Asprova implementation)
- Check more details regarding to new requirements from user
- 00:46 4.00 hours (Project progress work #673 (In Progress): [Settings] Asprova implementation)
- 00:46 4.00 hours (Project progress work #673 (In Progress): [Settings] Asprova implementation)
- Check master data
- 00:44 8.00 hours (Project progress work #673 (In Progress): [Settings] Asprova implementation)
28 Aug 2024
- 13:54 8.00 hours (Project progress work #673 (In Progress): [Settings] Asprova implementation)
- Try to generate the production schedule and check the item master