- 15:23 Project progress work #7021 (New): [Installation&On-site support]
- 15:23 Project progress work #7020 (New): [Coding]
- 15:23 Project progress work #7019 (New): [Internal Design]
- 15:22 Project progress work #7018 (New): [Requirement definition]
- 15:22 Parent project #7017: [PJ260057] Production management system for NIPPN (Thailand) Co.,Ltd. Feb 2026
- 1 Software
1-1 Senior engineer A development + installation work 1 month
1-2 Middle engineer B development + insta... - 14:47 Parent project #7017 (In Progress): [PJ260057] Production management system for NIPPN (Thailand) Co.,Ltd. Feb 2026
- 14:46 Project progress work #7016 (New): [Installation&On-site support]
- 14:46 Project progress work #7015 (New): [Coding]
- 14:45 Project progress work #7014 (New): [Internal Design]
- 14:45 Project progress work #7013 (New): [Requirement definition]
- 14:42 Parent project #7012: [PJ260056] Production management system for NIPPN (Thailand) Co.,Ltd. Jan 2026
- 1 Software
1-1 Senior engineer A development + installation work 1 month
1-2 Middle engineer B development + instal... - 13:50 Parent project #7012 (In Progress): [PJ260056] Production management system for NIPPN (Thailand) Co.,Ltd. Jan 2026