06 Mar 2026
- 09:32 Parent project #3399 (Closed): [PJ250110] WIFI Wiring modification work for NIPPN (Thailand) Co.,Ltd.
- 09:32 Project progress work #4359 (Closed): [Coding]
- 09:31 Project progress work #4358 (Closed): [Internal Design]
- 09:31 Project progress work #4357 (Closed): [Requirement definition]
- 09:31 Project progress work #4360 (Closed): [Installation&On-site support]
- 08:44 Project progress work #6804 (Closed): [Internal design] Meeting Spec CPF with team about Design UI
- 08:44 Project progress work #6804 (Closed): [Internal design] Meeting Spec CPF with team about Design UI
- 08:43 Project progress work #1626 (In Progress): [Internal Design] System Design
- 08:42 Project progress work #6803 (Closed): [Coding] "Test Delivery Note again because change structure and trigger warehouse continue from topic21"
- 08:42 Project progress work #6803 (Closed): [Coding] "Test Delivery Note again because change structure and trigger warehouse continue from topic21"
- 08:41 Project progress work #6802 (Closed): [Coding] add menu form withdraw weighing room in handy
- 08:41 Project progress work #6802 (Closed): [Coding] add menu form withdraw weighing room in handy