Project progress work #4360

closed

Parent project #3399: [PJ250110] WIFI Wiring modification work for NIPPN (Thailand) Co.,Ltd.

[Installation&On-site support]

Added by Siriwilai Chaiwattanaphon 2 months ago. Updated 15 days ago.

Status:
Closed
Priority:
Normal
Start date:
09 Jan 2026
Due date:
09 Jan 2026
% Done:

100%

Estimated time:
(Total: 8.00 h)
Finish date:
Programming skills:
No development
DB skills:
Not using
OS skills:
Not using

Subtasks 1 (0 open1 closed)

Project progress work #4466: [Installation&On-site support] Wiring LAN Cable and config access pointClosedPurinat Thongbaiyai09 Jan 202609 Jan 2026

Actions
Actions #1

Updated by Waraporn Promsopa 15 days ago

  • Status changed from New to Closed