01 Oct 2025
- 16:35 3.00 hours (Project progress work #1442 (Closed): [Coding] Software test)
- Improved the section that customers requested regarding updating duplicate files
29 Sep 2025
- 17:24 2.00 hours (Project progress work #1442 (Closed): [Coding] Software test)
- Test function with customer
23 Sep 2025
- 11:21 8.00 hours (Project progress work #1442 (Closed): [Coding] Software test)
- 11:10 2.00 hours (Project progress work #1441 (Closed): [Coding] Insert nst_file_import)
- 11:09 2.00 hours (Project progress work #1441 (Closed): [Coding] Insert nst_file_import)
- 11:09 2.00 hours (Project progress work #1441 (Closed): [Coding] Insert nst_file_import)
- 11:08 2.00 hours (Project progress work #1440 (Closed): [Coding] Import file Special Tag)
- 11:08 2.00 hours (Project progress work #1440 (Closed): [Coding] Import file Special Tag)
- 11:07 2.00 hours (Project progress work #1440 (Closed): [Coding] Import file Special Tag)