Activity
From 01 Nov 2024 to 10 Nov 2024
10 Nov 2024
- 21:11 4.00 hours (Project progress work #733 (Closed): Design and documentation)
- SIT test with k.puk and confirmation
08 Nov 2024
- 17:38 6.00 hours (Project progress work #743 (Closed): Development EDI system)
- fix calendar and layout print labels, Internal test with K.nack
- 17:36 6.00 hours (Project progress work #743 (Closed): Development EDI system)
- fix bug
06 Nov 2024
- 16:31 8.00 hours (Project progress work #743 (Closed): Development EDI system)
- Final test full system and fix bug
- 16:30 8.00 hours (Project progress work #743 (Closed): Development EDI system)
- Develop History tag page
05 Nov 2024
- 10:58 8.00 hours (Project progress work #743 (Closed): Development EDI system)
- Develop History tag page
02 Nov 2024
- 17:48 8.00 hours (Project progress work #743 (Closed): Development EDI system)
- Develop History tag page
01 Nov 2024
- 17:28 8.00 hours (Project progress work #743 (Closed): Development EDI system)
- Develop History tag page