25 Oct 2024
- 16:52 8.00 hours (Project progress work #721 (Closed): Modify PC Software.)
- Revise, Update and Test PC Software.
21 Oct 2024
- 17:18 8.00 hours (Project progress work #743 (Closed): Development EDI system)
- Develop Layout label
- 17:17 8.00 hours (Project progress work #743 (Closed): Development EDI system)
- Develop Print Issues tag page
- 17:17 8.00 hours (Project progress work #743 (Closed): Development EDI system)
- Develop Print Issues tag page
- 17:17 8.00 hours (Project progress work #743 (Closed): Development EDI system)
- Develop Print Issues tag page
17 Oct 2024
- 09:25 8.00 hours (Project progress work #743 (Closed): Development EDI system)
- Develop Print Issues tag page