18 May 2024

16:32 8.00 hours (Project progress work #470 (Closed): Packing List System)
Dev Packing List Jidapha Mangkhachot
16:14 8.00 hours (Project progress work #527 (Closed): Learning stock management system (handyterminal Java)/Development Scrap System for Nidec)
Design table is keep log approve flow. Priroj Neamjarn
16:14 8.00 hours (Project progress work #527 (Closed): Learning stock management system (handyterminal Java)/Development Scrap System for Nidec)
Design table is keep log approve flow. Priroj Neamjarn

17 May 2024

16:13 8.00 hours (Project progress work #527 (Closed): Learning stock management system (handyterminal Java)/Development Scrap System for Nidec)
Implement Approve flow Priroj Neamjarn
16:13 8.00 hours (Project progress work #527 (Closed): Learning stock management system (handyterminal Java)/Development Scrap System for Nidec)
Implement Approve flow Priroj Neamjarn

16 May 2024

17:18 8.00 hours (Project progress work #470 (Closed): Packing List System)
Dev Packing List Jidapha Mangkhachot
16:30 8.00 hours (Project progress work #470 (Closed): Packing List System)
Dev Packing List Jidapha Mangkhachot
16:20 8.00 hours (Project progress work #527 (Closed): Learning stock management system (handyterminal Java)/Development Scrap System for Nidec)
Implement Scrap system phase 2 (2/9) Priroj Neamjarn
16:19 8.00 hours (Project progress work #527 (Closed): Learning stock management system (handyterminal Java)/Development Scrap System for Nidec)
Implement Scrap system phase 2 (2/9) Priroj Neamjarn

15 May 2024

17:50 8.00 hours (Project progress work #470 (Closed): Packing List System)
Dev Packing List Jidapha Mangkhachot
17:49 8.00 hours (Project progress work #470 (Closed): Packing List System)
Dev Packing List Jidapha Mangkhachot
17:49 8.00 hours (Project progress work #470 (Closed): Packing List System)
Dev Packing List Jidapha Mangkhachot
17:49 8.00 hours (Project progress work #470 (Closed): Packing List System)
Dev Packing List Jidapha Mangkhachot
17:49 8.00 hours (Project progress work #470 (Closed): Packing List System)
Dev Packing List Jidapha Mangkhachot
17:48 8.00 hours (Project progress work #470 (Closed): Packing List System)
Dev Packing List Jidapha Mangkhachot
17:48 8.00 hours (Project progress work #470 (Closed): Packing List System)
Dev Packing List Jidapha Mangkhachot
17:48 8.00 hours (Project progress work #470 (Closed): Packing List System)
Dev Packing List Jidapha Mangkhachot
17:48 8.00 hours (Project progress work #470 (Closed): Packing List System)
Dev Packing List Jidapha Mangkhachot
17:47 8.00 hours (Project progress work #470 (Closed): Packing List System)
Dev Packing List Jidapha Mangkhachot
17:47 8.00 hours (Project progress work #470 (Closed): Packing List System)
Dev Packing List Jidapha Mangkhachot
17:47 8.00 hours (Project progress work #470 (Closed): Packing List System)
Dev Packing List Jidapha Mangkhachot
17:47 8.00 hours (Project progress work #470 (Closed): Packing List System)
Dev Packing List Jidapha Mangkhachot
17:46 8.00 hours (Project progress work #470 (Closed): Packing List System)
Dev Packing List Jidapha Mangkhachot
17:46 8.00 hours (Project progress work #470 (Closed): Packing List System)
Dev Packing List Jidapha Mangkhachot
17:46 8.00 hours (Project progress work #470 (Closed): Packing List System)
Dev Packing List Jidapha Mangkhachot
17:45 8.00 hours (Project progress work #470 (Closed): Packing List System)
Dev Packing List Jidapha Mangkhachot
17:45 8.00 hours (Project progress work #470 (Closed): Packing List System)
Dev Packing List Jidapha Mangkhachot
17:44 8.00 hours (Project progress work #470 (Closed): Packing List System)
Dev Packing List Jidapha Mangkhachot
17:42 8.00 hours (Project progress work #470 (Closed): Packing List System)
Dev Packing List Jidapha Mangkhachot
14:41 8.00 hours (Project progress work #470 (Closed): Packing List System)
Jidapha Mangkhachot
16:22 8.00 hours (Project progress work #527 (Closed): Learning stock management system (handyterminal Java)/Development Scrap System for Nidec)
Adjust code for Scrap Project Priroj Neamjarn
16:22 8.00 hours (Project progress work #527 (Closed): Learning stock management system (handyterminal Java)/Development Scrap System for Nidec)
Adjust code for Scrap Project Priroj Neamjarn

14 May 2024

15:33 8.00 hours (Project progress work #527 (Closed): Learning stock management system (handyterminal Java)/Development Scrap System for Nidec)
Meeting with user Scrap Project Priroj Neamjarn
15:32 8.00 hours (Project progress work #527 (Closed): Learning stock management system (handyterminal Java)/Development Scrap System for Nidec)
Meeting with user Scrap Project Priroj Neamjarn

13 May 2024

16:33 8.00 hours (Project progress work #527 (Closed): Learning stock management system (handyterminal Java)/Development Scrap System for Nidec)
Deploy project to customer server Priroj Neamjarn
16:13 8.00 hours (Project progress work #527 (Closed): Learning stock management system (handyterminal Java)/Development Scrap System for Nidec)
Deploy project to customer server Priroj Neamjarn
16:13 8.00 hours (Project progress work #527 (Closed): Learning stock management system (handyterminal Java)/Development Scrap System for Nidec)
Deploy project to customer server Priroj Neamjarn

10 May 2024

18:54 8.00 hours (Project progress work #470 (Closed): Packing List System)
Dev Packing List Jidapha Mangkhachot
16:21 8.00 hours (Project progress work #527 (Closed): Learning stock management system (handyterminal Java)/Development Scrap System for Nidec)
-Coding Font-end/Back-end for Document List and Document List items. Priroj Neamjarn
16:21 8.00 hours (Project progress work #527 (Closed): Learning stock management system (handyterminal Java)/Development Scrap System for Nidec)
-Coding Font-end/Back-end for Document List and Document List items. Priroj Neamjarn
 