Activity
From 03 Jun 2026 to 12 Jun 2026
12 Jun 2026
- 16:26 Project progress work #8540 (Closed): [Internal Design] Design Review for Belt Conveyor B,G-Line
- 16:24 Project progress work #8540 (Closed): [Internal Design] Design Review for Belt Conveyor B,G-Line
- 16:26 Project progress work #8539 (Closed): [Internal Design] 2D Drawing for Belt Conveyor B,G-Line
- 16:23 Project progress work #8539 (Closed): [Internal Design] 2D Drawing for Belt Conveyor B,G-Line
- 16:20 Project progress work #8538 (Closed): [Installation&On-site support] Transport part slat U2 line to Tomas tech W/H
- 16:20 Project progress work #8538 (Closed): [Installation&On-site support] Transport part slat U2 line to Tomas tech W/H
05 Jun 2026
- 16:06 Project progress work #8425 (Closed): [Requirement definition] Prepare and submit the Traceability System Specification R1 to the customer.
- 16:06 Project progress work #8425 (Closed): [Requirement definition] Prepare and submit the Traceability System Specification R1 to the customer.
- 16:05 Project progress work #8424 (Closed): [Requirement definition] Review HMI screens and operation flow with the customer.
- 16:05 Project progress work #8424 (Closed): [Requirement definition] Review HMI screens and operation flow with the customer.
- 16:02 Project progress work #8423 (Closed): [Coding] Design HIM Program
- 16:02 Project progress work #8423 (Closed): [Coding] Design HIM Program
- 15:58 Project progress work #8422 (Closed): [Internal Design] Update concept
- 15:57 Project progress work #8422 (Closed): [Internal Design] Update concept
- 15:55 Project progress work #8421 (Closed): [Requirement definition] Check inspection document
- 15:55 Project progress work #8421 (Closed): [Requirement definition] Check inspection document