Date User Activity Issue Comment Hours
29 Oct 2024 Nattapong Sukcharoen Installation Project progress work #796: [ Wring & Assembly ] Andon monitoring system Control cabinet 3 Set Assembly hardware and wiring 8.00 Actions
28 Oct 2024 Nattapong Sukcharoen Installation Project progress work #737: [ Installation & Support ] Installation and wiring andon project system support 8.00 Actions
28 Oct 2024 Phatthadon Inthachot Installation Project progress work #796: [ Wring & Assembly ] Andon monitoring system Control cabinet 3 Set Wiring cabinet 8.00 Actions
23 Oct 2024 Nattapong Sukcharoen Installation Project progress work #737: [ Installation & Support ] Installation and wiring andon project Support Installation 9.00 Actions
22 Oct 2024 Nattapong Sukcharoen Installation Project progress work #737: [ Installation & Support ] Installation and wiring andon project Support Installation 10.50 Actions
21 Oct 2024 Nattapong Sukcharoen Installation Project progress work #737: [ Installation & Support ] Installation and wiring andon project Support Installation 12.00 Actions
19 Oct 2024 Nattapong Sukcharoen Installation Project progress work #737: [ Installation & Support ] Installation and wiring andon project Support Installation 8.00 Actions
18 Oct 2024 Nattapong Sukcharoen Installation Project progress work #737: [ Installation & Support ] Installation and wiring andon project Support Installation 12.50 Actions
11 Oct 2024 Nattapong Sukcharoen Installation Project progress work #737: [ Installation & Support ] Installation and wiring andon project Support Installation 12.00 Actions
10 Oct 2024 Nattapong Sukcharoen Installation Project progress work #737: [ Installation & Support ] Installation and wiring andon project Support Installation 11.00 Actions
09 Oct 2024 Nattapong Sukcharoen Installation Project progress work #737: [ Installation & Support ] Installation and wiring andon project Support Installation 8.00 Actions
08 Oct 2024 Nattapong Sukcharoen Installation Project progress work #737: [ Installation & Support ] Installation and wiring andon project Support Installation 8.00 Actions
07 Oct 2024 Nattapong Sukcharoen Installation Project progress work #737: [ Installation & Support ] Installation and wiring andon project Support Installation 11.00 Actions
04 Oct 2024 Nattapong Sukcharoen Installation Project progress work #737: [ Installation & Support ] Installation and wiring andon project Support Installation 12.00 Actions
03 Oct 2024 Nattapong Sukcharoen Installation Project progress work #737: [ Installation & Support ] Installation and wiring andon project Support installation server pc rack 10.50 Actions
02 Oct 2024 Nattapong Sukcharoen Installation Project progress work #737: [ Installation & Support ] Installation and wiring andon project Support Installation Addon monitoring 10.50 Actions
02 Oct 2024 Nattapol Poeam Installation Project progress work #737: [ Installation & Support ] Installation and wiring andon project Support installation 8.00 Actions
01 Oct 2024 Nattapol Poeam Installation Project progress work #737: [ Installation & Support ] Installation and wiring andon project Support installation 8.00 Actions
30 Sep 2024 Nattapol Poeam Installation Project progress work #737: [ Installation & Support ] Installation and wiring andon project Support installation 8.00 Actions
27 Sep 2024 Nattapol Poeam Installation Project progress work #737: [ Installation & Support ] Installation and wiring andon project Support installation 8.00 Actions
26 Sep 2024 Nattapol Poeam Installation Project progress work #737: [ Installation & Support ] Installation and wiring andon project Support installation 8.00 Actions
19 Sep 2024 Nattapol Poeam Meeting Project progress work #720: Specification and system design Meeting about update specification and site survey 8.00 Actions
18 Sep 2024 Phatthadon Inthachot Make document Project progress work #700: PR Electrical part Make PO 8.00 Actions
18 Sep 2024 Nattapol Poeam Make document Project progress work #720: Specification and system design Make specification 8.00 Actions
02 Sep 2024 Nattapol Poeam Meeting Project progress work #720: Specification and system design Meeting about update progress work 8.00 Actions