Project

General

Profile

For internal project work assignment report without Nozaki

« April | June »

Apply Clear

Sunday Monday Tuesday Wednesday Thursday Friday Saturday
18

28

29

30

1

2

3

4

19

5

6

7

8

9

10

11

20

12

13

14

15

16

17

18

21

19

20

21

22

23

24

25

22

26

27

Project progress work #614: (Power Meter and CT ) Wirin... Project progress work #614: (Power Meter and CT ) Wiring and Installation

Project: JTEKT AUTOMOTIVE (THAILAND) CO.,LTD.
Status: New
Start date: 27 May 2024
Due date: 31 May 2024
Assignee: Panupong Raksakit
Priority: Normal

28

29

30

31

Project progress work #614: (Power Meter and CT ) Wirin... Project progress work #614: (Power Meter and CT ) Wiring and Installation

Project: JTEKT AUTOMOTIVE (THAILAND) CO.,LTD.
Status: New
Start date: 27 May 2024
Due date: 31 May 2024
Assignee: Panupong Raksakit
Priority: Normal

1