11 Jul 2024
- 20:35 8.00 hours (Project progress work #141 (Closed): [Task]Deverlop HMI Bekido and OA monitoring)
- Revised program section bekido,OEE formula
- 20:31 8.00 hours (Project progress work #141 (Closed): [Task]Deverlop HMI Bekido and OA monitoring)
- Revised program section weigth CT
- 20:33 8.00 hours (Project progress work #655 (Closed): [ Weekly work update meeting ] Minutes of Meeting IoT infrastructure system)
- Meeting about update progress work