From 15 May 2024 to 24 May 2024

24 May 2024

11:15 8.00 hours (Project progress work #599 (Closed): (Power Meter and CT ) Wiring and Installation Loop2 ,4 and Loop6 , )
meeting sumarize and prepare document for installation at (26/05/2024 Teeradon Yuensakul
11:13 8.00 hours (Project progress work #599 (Closed): (Power Meter and CT ) Wiring and Installation Loop2 ,4 and Loop6 , )
Teeradon Yuensakul
11:12 8.00 hours (Project progress work #599 (Closed): (Power Meter and CT ) Wiring and Installation Loop2 ,4 and Loop6 , )
prepare document for installation at (11/05/2024) Teeradon Yuensakul
11:11 8.00 hours (Project progress work #599 (Closed): (Power Meter and CT ) Wiring and Installation Loop2 ,4 and Loop6 , )
prepare document and prepare device for installation at JTEKT ( 22/05/2024) Teeradon Yuensakul
11:09 8.00 hours (Project progress work #599 (Closed): (Power Meter and CT ) Wiring and Installation Loop2 ,4 and Loop6 , )
Stand by and support customer after installation Teeradon Yuensakul
11:09 10.00 hours (Project progress work #599 (Closed): (Power Meter and CT ) Wiring and Installation Loop2 ,4 and Loop6 , )
CT Installation and wiring Teeradon Yuensakul

21 May 2024

08:34 8.00 hours (Project progress work #599 (Closed): (Power Meter and CT ) Wiring and Installation Loop2 ,4 and Loop6 , )
Prepare Device for Installation in at (18/05/2024 to 19/05/2024) Teeradon Yuensakul
08:33 8.00 hours (Project progress work #599 (Closed): (Power Meter and CT ) Wiring and Installation Loop2 ,4 and Loop6 , )
Monthly Meeting about work at shutdown factory (Installation ) Teeradon Yuensakul
08:31 12.30 hours (Project progress work #599 (Closed): (Power Meter and CT ) Wiring and Installation Loop2 ,4 and Loop6 , )
CT Installation and wiring Teeradon Yuensakul
08:30 9.30 hours (Project progress work #599 (Closed): (Power Meter and CT ) Wiring and Installation Loop2 ,4 and Loop6 , )
CT Installation and wiring Teeradon Yuensakul
08:28 9.30 hours (Project progress work #599 (Closed): (Power Meter and CT ) Wiring and Installation Loop2 ,4 and Loop6 , )
Power meter Installation and some wiring Teeradon Yuensakul
08:27 8.00 hours (Project progress work #599 (Closed): (Power Meter and CT ) Wiring and Installation Loop2 ,4 and Loop6 , )
Power Meter Installation Teeradon Yuensakul

15 May 2024

11:17 4.00 hours (Parent project #553 (Closed): [PJ240004]Infrastructure IoT system for Jtekt Automotive)
Internal test function program with K.Panupong Nattapol Poeam
11:00 8.00 hours (Project progress work #405 (Closed): [Requirement definition] Infrastructure IoT system for Jtekt Automotive)
Support installation Nattapol Poeam
 