Project

General

Profile

Activity

From 15 May 2024 to 24 May 2024

24 May 2024

11:08 Project progress work #599: (Power Meter and CT ) Wiring and Installation Loop2 ,4 and Loop6 ,
Loop4: Installation is 100% , Wiring is 60%
Loop6: Installation is 100% , Wiring is 70%
Teeradon Yuensakul

21 May 2024

08:25 Project progress work #599 (Closed): (Power Meter and CT ) Wiring and Installation Loop2 ,4 and Loop6 ,
CT and power meter was installed 100%
Just some CT and power meter wasn't installed , but it will be installed at ...
Teeradon Yuensakul
 

Also available in: Atom