21 May 2024

08:25 Project progress work #599 (Closed): (Power Meter and CT ) Wiring and Installation Loop2 ,4 and Loop6 ,
CT and power meter was installed 100%
Just some CT and power meter wasn't installed , but it will be installed at ...
Teeradon Yuensakul
 