Activity
From 11 Feb 2024 to 20 Feb 2024
19 Feb 2024
- 16:39 8.00 hours (Project progress work #124 (Closed): [Installation&On-site support] Production IoT system for JATH)
- Deverlop PLC calculate bekido function JTEKT
- 16:39 8.00 hours (Project progress work #124 (Closed): [Installation&On-site support] Production IoT system for JATH)
- Deverlop PLC calculate bekido function JTEKT
- 16:38 8.00 hours (Project progress work #124 (Closed): [Installation&On-site support] Production IoT system for JATH)
- Deverlop PLC calculate bekido function JTEKT
- 16:38 8.00 hours (Project progress work #124 (Closed): [Installation&On-site support] Production IoT system for JATH)
- Deverlop PLC calculate bekido function JTEKT
- 16:38 8.00 hours (Project progress work #124 (Closed): [Installation&On-site support] Production IoT system for JATH)
- Deverlop PLC calculate bekido function JTEKT
- 16:38 8.00 hours (Project progress work #124 (Closed): [Installation&On-site support] Production IoT system for JATH)
- Deverlop PLC calculate bekido function JTEKT
- 16:37 8.00 hours (Project progress work #141 (Closed): [Task]Deverlop HMI Bekido and OA monitoring)
- Meeting IOT Infrastructure
17 Feb 2024
- 09:59 8.00 hours (Project progress work #446 (Closed): [ Task ] Drawing design for Master control box)
- Design drawing
15 Feb 2024
- 09:05 8.00 hours (Project progress work #408 (Closed): [Installation&On-site support] Production IoT system for JATH)
- On site Jtekt test network aruba
- 09:04 8.00 hours (Project progress work #408 (Closed): [Installation&On-site support] Production IoT system for JATH)
- Configuration Access Point for connect with PLC By Aruba Network
- 09:04 8.00 hours (Project progress work #408 (Closed): [Installation&On-site support] Production IoT system for JATH)
- Configuration Access Point for connect with PLC By Aruba Network
12 Feb 2024
- 09:05 8.00 hours (Project progress work #408 (Closed): [Installation&On-site support] Production IoT system for JATH)
- Configuration Access Point for connect with PLC By Aruba Network
- 09:05 8.00 hours (Project progress work #408 (Closed): [Installation&On-site support] Production IoT system for JATH)
- Configuration Access Point for connect with PLC By Aruba Network
- 09:04 8.00 hours (Project progress work #408 (Closed): [Installation&On-site support] Production IoT system for JATH)
- Configuration Access Point for connect with PLC By Aruba Network
- 09:04 8.00 hours (Project progress work #408 (Closed): [Installation&On-site support] Production IoT system for JATH)
- Configuration Access Point for connect with PLC By Aruba Network
- 09:04 8.00 hours (Project progress work #408 (Closed): [Installation&On-site support] Production IoT system for JATH)
- Configuration Access Point for connect with PLC By Aruba Network
- 09:03 8.00 hours (Project progress work #408 (Closed): [Installation&On-site support] Production IoT system for JATH)
- Configuration Access Point for connect with PLC By Aruba Network
Also available in: Atom