Activity
From 03 Feb 2024 to 12 Feb 2024
12 Feb 2024
- 09:05 8.00 hours (Project progress work #408 (Closed): [Installation&On-site support] Production IoT system for JATH)
- Configuration Access Point for connect with PLC By Aruba Network
- 09:05 8.00 hours (Project progress work #408 (Closed): [Installation&On-site support] Production IoT system for JATH)
- Configuration Access Point for connect with PLC By Aruba Network
- 09:04 8.00 hours (Project progress work #408 (Closed): [Installation&On-site support] Production IoT system for JATH)
- Configuration Access Point for connect with PLC By Aruba Network
- 09:04 8.00 hours (Project progress work #408 (Closed): [Installation&On-site support] Production IoT system for JATH)
- Configuration Access Point for connect with PLC By Aruba Network
- 09:04 8.00 hours (Project progress work #408 (Closed): [Installation&On-site support] Production IoT system for JATH)
- Configuration Access Point for connect with PLC By Aruba Network
- 09:03 8.00 hours (Project progress work #408 (Closed): [Installation&On-site support] Production IoT system for JATH)
- Configuration Access Point for connect with PLC By Aruba Network
09 Feb 2024
- 09:09 8.00 hours (Project progress work #412 (Closed): [Installation&On-site support] Hardware installation for Infrastructure IoT Project)
- Installation FAC3
- 08:15 8.00 hours (Project progress work #412 (Closed): [Installation&On-site support] Hardware installation for Infrastructure IoT Project)
- Deverlop PLC calculate bekido function JTEKT
- 08:15 8.00 hours (Project progress work #412 (Closed): [Installation&On-site support] Hardware installation for Infrastructure IoT Project)
- Deverlop PLC calculate bekido function JTEKT
- 08:14 8.00 hours (Project progress work #412 (Closed): [Installation&On-site support] Hardware installation for Infrastructure IoT Project)
- Deverlop PLC calculate bekido function JTEKT
- 08:14 8.00 hours (Project progress work #412 (Closed): [Installation&On-site support] Hardware installation for Infrastructure IoT Project)
- Deverlop PLC calculate bekido function JTEKT
- 08:14 8.00 hours (Project progress work #412 (Closed): [Installation&On-site support] Hardware installation for Infrastructure IoT Project)
- Deverlop PLC calculate bekido function JTEKT
- 08:14 8.00 hours (Project progress work #412 (Closed): [Installation&On-site support] Hardware installation for Infrastructure IoT Project)
- Deverlop PLC calculate bekido function JTEKT
- 08:13 8.00 hours (Project progress work #412 (Closed): [Installation&On-site support] Hardware installation for Infrastructure IoT Project)
- Deverlop PLC calculate bekido function JTEKT
- 08:13 8.00 hours (Project progress work #412 (Closed): [Installation&On-site support] Hardware installation for Infrastructure IoT Project)
- Deverlop PLC calculate bekido function JTEKT
- 08:13 8.00 hours (Project progress work #412 (Closed): [Installation&On-site support] Hardware installation for Infrastructure IoT Project)
- Deverlop PLC calculate bekido function JTEKT
- 08:13 8.00 hours (Project progress work #412 (Closed): [Installation&On-site support] Hardware installation for Infrastructure IoT Project)
- Deverlop PLC calculate bekido function JTEKT
- 08:12 8.00 hours (Project progress work #412 (Closed): [Installation&On-site support] Hardware installation for Infrastructure IoT Project)
- Deverlop PLC calculate bekido function JTEKT
- 08:12 8.00 hours (Project progress work #412 (Closed): [Installation&On-site support] Hardware installation for Infrastructure IoT Project)
- Deverlop PLC calculate bekido function JTEKT
- 08:20 8.00 hours (Project progress work #413 (Closed): [Installation&On-site support] Software installation for Infrastructure IoT Project)
- Installation Electrical cabinet
- 08:20 8.00 hours (Project progress work #413 (Closed): [Installation&On-site support] Software installation for Infrastructure IoT Project)
- Installation Electrical cabinet
- 08:18 8.00 hours (Project progress work #413 (Closed): [Installation&On-site support] Software installation for Infrastructure IoT Project)
- Program and Dashboard Development
- 08:18 8.00 hours (Project progress work #413 (Closed): [Installation&On-site support] Software installation for Infrastructure IoT Project)
- Program and Dashboard Development
- 08:18 8.00 hours (Project progress work #413 (Closed): [Installation&On-site support] Software installation for Infrastructure IoT Project)
- Program and Dashboard Development
- 08:17 8.00 hours (Project progress work #413 (Closed): [Installation&On-site support] Software installation for Infrastructure IoT Project)
- Program and Dashboard Development
- 08:17 8.00 hours (Project progress work #413 (Closed): [Installation&On-site support] Software installation for Infrastructure IoT Project)
- Program and Dashboard Development
- 08:17 8.00 hours (Project progress work #413 (Closed): [Installation&On-site support] Software installation for Infrastructure IoT Project)
- Program and Dashboard Development
- 08:16 8.00 hours (Project progress work #413 (Closed): [Installation&On-site support] Software installation for Infrastructure IoT Project)
- Program and Dashboard Development
- 08:16 8.00 hours (Project progress work #413 (Closed): [Installation&On-site support] Software installation for Infrastructure IoT Project)
- Program and Dashboard Development
- 08:16 8.00 hours (Project progress work #413 (Closed): [Installation&On-site support] Software installation for Infrastructure IoT Project)
- Program and Dashboard Development
- 08:14 8.00 hours (Project progress work #413 (Closed): [Installation&On-site support] Software installation for Infrastructure IoT Project)
- Program JTEKT bekido
- 08:14 8.00 hours (Project progress work #413 (Closed): [Installation&On-site support] Software installation for Infrastructure IoT Project)
- Program JTEKT bekido
- 08:13 8.00 hours (Project progress work #413 (Closed): [Installation&On-site support] Software installation for Infrastructure IoT Project)
- Program JTEKT bekido
- 08:13 8.00 hours (Project progress work #413 (Closed): [Installation&On-site support] Software installation for Infrastructure IoT Project)
- Program JTEKT bekido
- 08:13 8.00 hours (Project progress work #413 (Closed): [Installation&On-site support] Software installation for Infrastructure IoT Project)
- Program JTEKT bekido
- 08:12 8.00 hours (Project progress work #413 (Closed): [Installation&On-site support] Software installation for Infrastructure IoT Project)
- Program JTEKT bekido
- 08:12 8.00 hours (Project progress work #413 (Closed): [Installation&On-site support] Software installation for Infrastructure IoT Project)
- Program JTEKT bekido
- 08:12 8.00 hours (Project progress work #413 (Closed): [Installation&On-site support] Software installation for Infrastructure IoT Project)
- Program JTEKT bekido
- 08:12 8.00 hours (Project progress work #413 (Closed): [Installation&On-site support] Software installation for Infrastructure IoT Project)
- Program JTEKT bekido
- 08:11 8.00 hours (Project progress work #413 (Closed): [Installation&On-site support] Software installation for Infrastructure IoT Project)
- Program JTEKT bekido
- 08:11 8.00 hours (Project progress work #413 (Closed): [Installation&On-site support] Software installation for Infrastructure IoT Project)
- Program JTEKT bekido
- 08:10 8.00 hours (Project progress work #413 (Closed): [Installation&On-site support] Software installation for Infrastructure IoT Project)
- Program JTEKT bekido
- 08:10 8.00 hours (Project progress work #413 (Closed): [Installation&On-site support] Software installation for Infrastructure IoT Project)
- Program JTEKT bekido
- 08:10 8.00 hours (Project progress work #413 (Closed): [Installation&On-site support] Software installation for Infrastructure IoT Project)
- Program JTEKT bekido
- 08:09 8.00 hours (Project progress work #413 (Closed): [Installation&On-site support] Software installation for Infrastructure IoT Project)
- Lernning PLC Keyence KV-8000
- 08:09 8.00 hours (Project progress work #413 (Closed): [Installation&On-site support] Software installation for Infrastructure IoT Project)
- Lernning PLC Keyence KV-8000
- 08:09 8.00 hours (Project progress work #413 (Closed): [Installation&On-site support] Software installation for Infrastructure IoT Project)
- Lernning PLC Keyence KV-8000
- 08:07 8.00 hours (Project progress work #413 (Closed): [Installation&On-site support] Software installation for Infrastructure IoT Project)
- Lernning PLC Keyence KV-8000
- 08:07 8.00 hours (Project progress work #413 (Closed): [Installation&On-site support] Software installation for Infrastructure IoT Project)
- Lernning PLC Keyence KV-8000
- 08:07 8.00 hours (Project progress work #413 (Closed): [Installation&On-site support] Software installation for Infrastructure IoT Project)
- Lernning PLC Keyence KV-8000
- 08:06 8.00 hours (Project progress work #413 (Closed): [Installation&On-site support] Software installation for Infrastructure IoT Project)
- Lernning PLC Keyence KV-8000
08 Feb 2024
- 08:20 8.00 hours (Project progress work #411 (Closed): [ Task ] Drawing design for Master control box)
- Sick
07 Feb 2024
- 15:44 8.00 hours (Project progress work #411 (Closed): [ Task ] Drawing design for Master control box)
- Sick
- 15:42 8.00 hours (Project progress work #411 (Closed): [ Task ] Drawing design for Master control box)
- Design drawing
- 15:35 8.00 hours (Project progress work #411 (Closed): [ Task ] Drawing design for Master control box)
- Sick
06 Feb 2024
- 16:41 8.00 hours (Project progress work #396 (Closed): Meeting From JATH about IoT of infrastructure)
- Meeting IOT Infrastructure
- 16:39 4.00 hours (Project progress work #410 (Closed): [ Task ] Program and Dashboard Development )
- Deverlop PLC calculate bekido function LINE LINK PRODUCTION
- 16:37 4.00 hours (Project progress work #428 (Closed): Servey plant installation power meter to panel control)
- Meeting From JATH about IoT of infrastructure
- 16:33 8.00 hours (Project progress work #119 (Closed): [Internal Design] DB and various functions, man-hour calculation)
- Function PLC Data link