From 03 Feb 2024 to 12 Feb 2024

12 Feb 2024

09:02 Project progress work #408 (In Progress): [Installation&On-site support] Production IoT system for JATH
Woraphong Wernsantiah

09 Feb 2024

09:09 Project progress work #412: [Installation&On-site support] Hardware installation for Infrastructure IoT Project
Installation FAC3
-Lan wiring MN1,MN2
-Lanwiring CEPS1,CEPS2
-Cabinate MN1,MN2
-Cabinate CEPS1,CEPS2
Santi Srichankaew

07 Feb 2024

22:10 Project progress work #428 (Close request): Servey plant installation power meter to panel control
Kittisak Isarapongporn
22:10 Project progress work #426 (Close request): Configuration Between PLC And HMI&Dashboard
Kittisak Isarapongporn
22:10 Project progress work #396 (Close request): Meeting From JATH about IoT of infrastructure
Kittisak Isarapongporn
22:10 Project progress work #370 (Close request): Install equipment & wiring in the control box 14 set.
Kittisak Isarapongporn
22:10 Project progress work #355 (Close request): Deverlop OEE % data analysis
Kittisak Isarapongporn
22:10 Project progress work #328 (Close request): Crate IoT data collection box for JATH
Kittisak Isarapongporn

06 Feb 2024

16:41 Project progress work #396 (Confirmation request): Meeting From JATH about IoT of infrastructure
Meeting IOT Infrastructure Santi Srichankaew
16:37 Project progress work #428 (Confirmation request): Servey plant installation power meter to panel control
Meeting From JATH about IoT of infrastructure Santi Srichankaew
16:36 Project progress work #428 (Closed): Servey plant installation power meter to panel control
Servey plant installation power meter to panel control Fac 1,2,3
Servey plant installation flow meter tube air compr...
Santi Srichankaew
16:33 Project progress work #119: [Internal Design] DB and various functions, man-hour calculation
[ Task ]
- Test function PLC Link beeteen Fac1 to Fac3
Nattapol Poeam
 