Activity
From 17 Jan 2024 to 26 Jan 2024
24 Jan 2024
- 07:50 8.00 hours (Project progress work #370 (Closed): Install equipment & wiring in the control box 14 set.)
- Wiring cable in the cabinet
- 07:49 8.00 hours (Project progress work #370 (Closed): Install equipment & wiring in the control box 14 set.)
- Wiring cable in the cabinet
20 Jan 2024
- 16:58 8.00 hours (Project progress work #370 (Closed): Install equipment & wiring in the control box 14 set.)
- Wiring cable in the cabinet
- 16:58 8.00 hours (Project progress work #370 (Closed): Install equipment & wiring in the control box 14 set.)
- Wiring cable in the cabinet
19 Jan 2024
- 09:43 8.00 hours (Project progress work #349 (Closed): Test WiFi data transmission between PLC to PLC)
- Develop PLC To PLC Data by Wifi
- 09:42 8.00 hours (Project progress work #349 (Closed): Test WiFi data transmission between PLC to PLC)
- Develop PLC To PLC Data by Wifi
- 09:41 8.00 hours (Project progress work #349 (Closed): Test WiFi data transmission between PLC to PLC)
- Develop PLC To PLC Data by Wifi
- 09:41 8.00 hours (Project progress work #349 (Closed): Test WiFi data transmission between PLC to PLC)
- Develop PLC To PLC Data by Wifi
18 Jan 2024
- 17:03 8.00 hours (Project progress work #370 (Closed): Install equipment & wiring in the control box 14 set.)
- 10:30 8.00 hours (Project progress work #370 (Closed): Install equipment & wiring in the control box 14 set.)
- Install equipment in the control box.
17 Jan 2024
- 08:01 8.00 hours (Project progress work #345 (Closed): Design ,Install & Wiring in control box)
- Meeting at JTEKT.
Also available in: Atom