10 Jan 2024
09 Jan 2024
- 16:30 Project progress work #349 (In Progress): Test WiFi data transmission between PLC to PLC
- 08:08 Project progress work #355 (Confirmation request): Deverlop OEE % data analysis
08 Jan 2024
- 17:53 Project progress work #344 (Closed): Learning Keyence PLC JTEKT IOT.
- 08:16 Project progress work #344 (Close request): Learning Keyence PLC JTEKT IOT.
- 17:53 Project progress work #341 (Closed): Price compare from supplier & Design drawing
- 17:53 Project progress work #332 (Closed): Price compare from supplier & Design drawing
- 17:53 Project progress work #120 (Closed): [Coding&UT] KV8000 Touch display and XD02 monitor screen
- 16:38 Project progress work #355 (Closed): Deverlop OEE % data analysis
- Deverlop OEE % data analysis
Detail :
Code plc desogner OEE