Activity
From 27 Dec 2023 to 05 Jan 2024
05 Jan 2024
- 12:04 Project progress work #349 (Closed): Test WiFi data transmission between PLC to PLC
- - Dashboard control
- Record data by Host link
- FTP Data
- Remote I/O
04 Jan 2024
- 09:56 Project progress work #345 (Closed): Design ,Install & Wiring in control box
- -Install Equipment
- Wiring in control box
28 Dec 2023
- 10:12 Project progress work #341 (Close request): Price compare from supplier & Design drawing
- 10:12 Project progress work #332 (Close request): Price compare from supplier & Design drawing
- 10:12 Project progress work #120 (Close request): [Coding&UT] KV8000 Touch display and XD02 monitor screen
27 Dec 2023
- 16:42 Project progress work #344 (Closed): Learning Keyence PLC JTEKT IOT.
- Learning Keyence PLC JTEKT IOT.
- 16:41 Project progress work #120 (Confirmation request): [Coding&UT] KV8000 Touch display and XD02 monitor screen
- [Fllow] #141 ==> http://node25444-tom-demo-01.proen.app.ruk-com.cloud:11447/issues/141
- 16:40 Project progress work #332 (Confirmation request): Price compare from supplier & Design drawing