Activity
From 12 Oct 2023 to 21 Oct 2023
21 Oct 2023
- 15:36 Project progress work #141 (Closed): [Task]Deverlop HMI Bekido and OA monitoring
- Deverlop HMI Bekido and OA monitoring
PLC creat program - 15:31 Sales support #139 (Closed): Meeting Kick off IOT bekido and OA monitoring
- -Scope of work
-Part support
-Schedule work flow
-HMI monitor viewer
-Layout plants
Next metting
24/10/2023 ...
19 Oct 2023
- 12:31 Project progress work #125 (Closed): [Installation&On-site support] Production IoT system for JATH
- 12:29 Project progress work #124 (Closed): [Installation&On-site support] Production IoT system for JATH
- 12:29 Project progress work #123 (Closed): [Installation&On-site support] Production IoT system for JATH
- 12:24 Project progress work #122 (Closed): [Coding&UT] PHP web function
- 12:23 Project progress work #121 (Closed): [Coding&UT] PLC and DB linkage function
- 12:22 Project progress work #120 (Closed): [Coding&UT] KV8000 Touch display and XD02 monitor screen
- 12:21 Project progress work #119 (Closed): [Internal Design] DB and various functions, man-hour calculation
17 Oct 2023