19 Oct 2023
- 12:31 Project progress work #125 (Closed): [Installation&On-site support] Production IoT system for JATH
- 12:29 Project progress work #124 (Closed): [Installation&On-site support] Production IoT system for JATH
- 12:29 Project progress work #123 (Closed): [Installation&On-site support] Production IoT system for JATH
- 12:24 Project progress work #122 (Closed): [Coding&UT] PHP web function
- 12:23 Project progress work #121 (Closed): [Coding&UT] PLC and DB linkage function
- 12:22 Project progress work #120 (Closed): [Coding&UT] KV8000 Touch display and XD02 monitor screen
- 12:21 Project progress work #119 (Closed): [Internal Design] DB and various functions, man-hour calculation