10

1

2

Project progress work #3274: Software installation [Tapi... Project progress work #3274: Software installation [Taping Label System]

Project: Asian Stanley. International Limited
Status: New
Start date: 02 Mar 2026
Due date: 04 Mar 2026
Assignee: Soraya Norasing
Priority: Normal

3

4

Project progress work #3274: Software installation [Tapi... Project progress work #3274: Software installation [Taping Label System]

Project: Asian Stanley. International Limited
Status: New
Start date: 02 Mar 2026
Due date: 04 Mar 2026
Assignee: Soraya Norasing
Priority: Normal

5

Project progress work #3275: [Installation&On-site suppo... Project progress work #3275: [Installation&On-site support] Teaching for UT (Shift A)

Project: Asian Stanley. International Limited
Status: New
Start date: 05 Mar 2026
Due date: 05 Mar 2026
Assignee: Soraya Norasing
Priority: Normal

6

7

11

8

9

Project progress work #3276: [Installation&On-site suppo... Project progress work #3276: [Installation&On-site support] Teaching for UT (Shift B)

Project: Asian Stanley. International Limited
Status: New
Start date: 09 Mar 2026
Due date: 09 Mar 2026
Assignee: Soraya Norasing
Priority: Normal

10

Project progress work #3278: [Installation&On-site suppo... Project progress work #3278: [Installation&On-site support] Supports user feedback

Project: Asian Stanley. International Limited
Status: New
Start date: 10 Mar 2026
Due date: 13 Mar 2026
Assignee: Soraya Norasing
Priority: Normal
Project progress work #3277: [Installation&On-site suppo... Project progress work #3277: [Installation&On-site support] User Testing & Trial

Project: Asian Stanley. International Limited
Status: New
Start date: 10 Mar 2026
Due date: 13 Mar 2026
Assignee: Soraya Norasing
Priority: Normal

11

12

13

Project progress work #3278: [Installation&On-site suppo... Project progress work #3278: [Installation&On-site support] Supports user feedback

Project: Asian Stanley. International Limited
Status: New
Start date: 10 Mar 2026
Due date: 13 Mar 2026
Assignee: Soraya Norasing
Priority: Normal
Project progress work #3277: [Installation&On-site suppo... Project progress work #3277: [Installation&On-site support] User Testing & Trial

Project: Asian Stanley. International Limited
Status: New
Start date: 10 Mar 2026
Due date: 13 Mar 2026
Assignee: Soraya Norasing
Priority: Normal

14

12

15

16

Project progress work #3280: [Installation&On-site suppo... Project progress work #3280: [Installation&On-site support] Go live

Project: Asian Stanley. International Limited
Status: New
Start date: 16 Mar 2026
Due date: 16 Mar 2026
Assignee: Soraya Norasing
Priority: Normal
Project progress work #3279: [Installation&On-site suppo... Project progress work #3279: [Installation&On-site support] Teaching for Go live

Project: Asian Stanley. International Limited
Status: New
Start date: 16 Mar 2026
Due date: 16 Mar 2026
Assignee: Soraya Norasing
Priority: Normal
Project progress work #3266: [Installation&On-site support] Project progress work #3266: [Installation&On-site support]

Project: Asian Stanley. International Limited
Status: New
Start date: 05 Feb 2026
Due date: 16 Mar 2026
Assignee: Soraya Norasing
Priority: Normal
Parent project #3248: [PJ2500XX] Handy terminal P... Parent project #3248: [PJ2500XX] Handy terminal Process control system modification fee

Project: Asian Stanley. International Limited
Status: In Progress
Start date: 01 Oct 2025
Due date: 16 Mar 2026
Assignee: Soraya Norasing
Priority: Normal

17

18

19

20

21

13

22

23

24

25

26

27

28

14

29

30

31

1

2

3

4

issue beginning this day issue ending this day issue beginning and ending this day