11 Apr 2025
- 16:28 8.00 hours (Project progress work #995 (Closed): get requirement and create specification Doc. [Calling maintenance staff system])
- meeting with customer, update all project , modify spec and operation flow
- 16:24 4.00 hours (Project progress work #995 (Closed): get requirement and create specification Doc. [Calling maintenance staff system])
- create specification Doc. R1 : operation, flow chart, document infomation
- 16:23 2.00 hours (Project progress work #995 (Closed): get requirement and create specification Doc. [Calling maintenance staff system])
- create specification Doc. R1 : config, operation, flow chart
- 16:27 2.00 hours (Project progress work #784 (Closed): [Colding] Handy terminal BT-A500 Java application (Process Control System))
- Verify the accuracy of the report
- 16:19 1.00 hour (Project progress work #784 (Closed): [Colding] Handy terminal BT-A500 Java application (Process Control System))
- support user online: update plan, query report for customer,
- 16:19 8.00 hours (Project progress work #784 (Closed): [Colding] Handy terminal BT-A500 Java application (Process Control System))
- Verify the accuracy of the report with K.fight, support user online:query report for customer,
- 16:19 1.00 hour (Project progress work #784 (Closed): [Colding] Handy terminal BT-A500 Java application (Process Control System))
- support user online: update plan, query report for customer,
- 16:26 6.00 hours (Project progress work #788 (Closed): [Colding] Handy terminal BT-A500 Java application [Label printing classify rank system])
- meeting with customer and modify spec
04 Apr 2025
- 12:07 5.00 hours (Project progress work #788 (Closed): [Colding] Handy terminal BT-A500 Java application [Label printing classify rank system])
- Meeting with customer, modify spec,
- 11:59 8.00 hours (Project progress work #784 (Closed): [Colding] Handy terminal BT-A500 Java application (Process Control System))
- test report with K.fight and Verify the accuracy of all 4 menu reports.
- 11:58 8.00 hours (Project progress work #784 (Closed): [Colding] Handy terminal BT-A500 Java application (Process Control System))
- Metting with K.Kam about dashboard, meeting with K.fight about report and test
- 11:57 8.00 hours (Project progress work #784 (Closed): [Colding] Handy terminal BT-A500 Java application (Process Control System))
- meeting with customer on site about dashboard, print rank classify
- 11:51 8.00 hours (Project progress work #786 (Closed): [Colding] Handy terminal BT-A500 Java application [Label printing system (Taping)])
- meeting with K.fight test report & master , support usert add printer