20 Nov 2024
- 15:06 4.00 hours (Project progress work #760 (Closed): Production Control Budomari Information board (Display))
- Display 1 & Display 2 Query fixed
17 Nov 2024
- 23:23 1.00 hour (Project progress work #754 (Closed): [Design] Design and consult)
- Meeting about application design of handy working in an offline mode
16 Nov 2024
- 22:11 8.00 hours (Project progress work #784 (Closed): [Colding] Handy terminal BT-A500 Java application (Process Control System))
- modify HT function wirebond & api
- 22:11 8.00 hours (Project progress work #784 (Closed): [Colding] Handy terminal BT-A500 Java application (Process Control System))
- modify HT function wirebond