23 Aug 2024

17:29 6.00 hours (Project progress work #647 (Closed): [Coding]ASI - Process Control System Phase2 -C# Windows app)
fix program bugs report Jidapha Mangkhachot
17:25 4.00 hours (Project progress work #647 (Closed): [Coding]ASI - Process Control System Phase2 -C# Windows app)
fix program bugs report Jidapha Mangkhachot
17:24 8.00 hours (Project progress work #647 (Closed): [Coding]ASI - Process Control System Phase2 -C# Windows app)
fix program bugs report Jidapha Mangkhachot
17:24 8.00 hours (Project progress work #647 (Closed): [Coding]ASI - Process Control System Phase2 -C# Windows app)
fix program bugs report Jidapha Mangkhachot

19 Aug 2024

17:22 3.00 hours (Project progress work #647 (Closed): [Coding]ASI - Process Control System Phase2 -C# Windows app)
Jidapha Mangkhachot

16 Aug 2024

09:20 3.00 hours (Project progress work #647 (Closed): [Coding]ASI - Process Control System Phase2 -C# Windows app)
fix program bugs report Jidapha Mangkhachot

15 Aug 2024

14:02 8.00 hours (Project progress work #674 (Closed): [Installation]Process Control System phase2)
Soraya Norasing
14:00 8.00 hours (Project progress work #674 (Closed): [Installation]Process Control System phase2)
Installation&On-site support Soraya Norasing
14:00 8.00 hours (Project progress work #674 (Closed): [Installation]Process Control System phase2)
Installation&On-site support Soraya Norasing
14:00 8.00 hours (Project progress work #465 (Closed): [Coding]ASI - Process Control System Phase2 -Java)
test and fix bug program on handy Soraya Norasing
 