- 10:43 8.00 hours (Project progress work #8 (Closed): Support installation for power supply and LAN cable for 50 points)
- Installation&On-site support
- 10:43 8.00 hours (Project progress work #8 (Closed): Support installation for power supply and LAN cable for 50 points)
- Installation&On-site support
15 Feb 2024
- 16:29 4.00 hours (Project progress work #376 (Closed): Disscuss about new screen concept with ASI menber)
- Meeting and discuss new function