29 Oct 2023

11:26 1.00 hour (Project progress work #8 (Closed): Support installation for power supply and LAN cable for 50 points)
Ryo Nozaki

27 Oct 2023

10:08 1.00 hour (Sales support #36 (Closed): UPS can not use in some position at LINE model H9J )
Arunwit Isarapongporn
09:52 1.00 hour (Project progress work #8 (Closed): Support installation for power supply and LAN cable for 50 points)
Arunwit Isarapongporn

26 Oct 2023

17:15 4.00 hours (Problem-Bug #152 (Closed): Found the incorrect barcode generated)
Modify the print label app and released the new version 2.2.4 Kittisak Isarapongporn
13:36 8.00 hours (Project progress work #59 (Closed): Support installation HT-Label printing system)
Soraya Norasing

25 Oct 2023

12:18 8.00 hours (Project progress work #95 (Closed): Support installation for power supply and LAN cable for 20 points)
Arunwit Isarapongporn
12:11 8.00 hours (Project progress work #8 (Closed): Support installation for power supply and LAN cable for 50 points)
Arunwit Isarapongporn

24 Oct 2023

19:45 8.00 hours (Project progress work #59 (Closed): Support installation HT-Label printing system)
Soraya Norasing

21 Oct 2023

13:38 8.00 hours (Project progress work #59 (Closed): Support installation HT-Label printing system)
Soraya Norasing

20 Oct 2023

13:48 4.00 hours (Project progress work #8 (Closed): Support installation for power supply and LAN cable for 50 points)
Check site Ryo Nozaki
07:40 8.00 hours (Project progress work #8 (Closed): Support installation for power supply and LAN cable for 50 points)
Arunwit Isarapongporn
 