Hours: 1100.50

Date User Activity Issue Comment Hours
20 Sep 2024 Arunwit Isarapongporn Meeting Project progress work #603: Support Online support about modify BOM&Planning 8.00 Actions
18 Sep 2024 Arunwit Isarapongporn Installation Parent project #704: [PJ240038] Handy terminal app Installation&On-site support 8.00 Actions
17 Sep 2024 Arunwit Isarapongporn Development Parent project #704: [PJ240038] Handy terminal app Modify&Test Handy terminal app 8.00 Actions
16 Sep 2024 Arunwit Isarapongporn Development Parent project #704: [PJ240038] Handy terminal app Modify&Test Handy terminal app 8.00 Actions
07 Sep 2024 Arunwit Isarapongporn Development Parent project #704: [PJ240038] Handy terminal app Modify Handy terminal app 8.00 Actions
06 Sep 2024 Arunwit Isarapongporn Development Parent project #704: [PJ240038] Handy terminal app Modify Handy terminal app 8.00 Actions
05 Sep 2024 Arunwit Isarapongporn Development Parent project #704: [PJ240038] Handy terminal app Modify Handy terminal app 8.00 Actions
03 Sep 2024 Arunwit Isarapongporn Installation Parent project #704: [PJ240038] Handy terminal app install OCR matching and check label master & app menu(Clear, MainMenu) 8.00 Actions
29 Aug 2024 Arunwit Isarapongporn Development Parent project #704: [PJ240038] Handy terminal app Modify Handy terminal app 8.00 Actions
28 Aug 2024 Arunwit Isarapongporn Development Parent project #704: [PJ240038] Handy terminal app Modify Handy terminal app 8.00 Actions
27 Aug 2024 Arunwit Isarapongporn Development Parent project #704: [PJ240038] Handy terminal app Modify Handy terminal app 8.00 Actions
26 Aug 2024 Arunwit Isarapongporn Development Parent project #704: [PJ240038] Handy terminal app Modify Handy terminal app 8.00 Actions
22 Aug 2024 Arunwit Isarapongporn Installation Project progress work #603: Support Installation&On-site support 8.00 Actions
22 Aug 2024 Kittisak Isarapongporn Development Project progress work #652: System support and maintenance Modify repack label function (cont.) 5.00 Actions
21 Aug 2024 Arunwit Isarapongporn Installation Project progress work #603: Support Installation&On-site support 8.00 Actions
21 Aug 2024 Kittisak Isarapongporn Development Project progress work #652: System support and maintenance Modify repack label function 3.00 Actions
10 Aug 2024 Arunwit Isarapongporn Meeting Project progress work #603: Support On-site support 8.00 Actions
09 Aug 2024 Arunwit Isarapongporn Meeting Project progress work #603: Support On-site support 8.00 Actions
07 Aug 2024 Kittisak Isarapongporn Development Project progress work #652: System support and maintenance Install and support the new HT firmware. Fix tag generator web page about item unit on repack function. 4.00 Actions
05 Aug 2024 Kittisak Isarapongporn Development Project progress work #652: System support and maintenance Modify HT outbound function to support to scan the label tag that are not in the FIFO list. 8.00 Actions
02 Aug 2024 Arunwit Isarapongporn Meeting Project progress work #94: [On-site support]Support after cutover Support to start using WMS the system for handy terminal & pegasus system 8.00 Actions
02 Aug 2024 Kittisak Isarapongporn Development Project progress work #652: System support and maintenance Find and fix HT outbound function 8.00 Actions
02 Aug 2024 Kamol Anekchatnuntakool Development Project progress work #676: Develop HT Software for scan TAG. Develop HT Software for scan TAG. 8.00 Actions
01 Aug 2024 Kamol Anekchatnuntakool Development Project progress work #676: Develop HT Software for scan TAG. Develop HT Software for scan TAG. 8.00 Actions
31 Jul 2024 Kamol Anekchatnuntakool Development Project progress work #676: Develop HT Software for scan TAG. Develop HT Software for scan TAG. 3.00 Actions